Cheyenne Light Files Three Microsoft Data Center Agreements at FERC 'Out of an Abundance of Caution,' With the Costs Booked at $0

In Docket ER27-634, the Black Hills utility asks FERC to accept facility agreements for Microsoft's Meadowlark, Equality and Frontier campuses while arguing they provide no FERC-jurisdictional service. Microsoft prepays the lines and substations; the load forecasts and cost caps are redacted.

Owen HollisLoad Factor News

Load Ledger
ItemBodyStageSrc
Facility Expansion Agreements, Meadowlark, Equality and Frontier campuses (Rate Schedule Nos. 13, 14, 15)FERC Docket ER27-634 (Cheyenne Light)filed Nov. 24, 2026; requested effective Dec. 24, 2026[1]
Certificates of public convenience and necessity for the facilitiesWyoming Public Service Commissionto be filed; required before construction[1]
W.S. 37-3-116, large-customer service agreements (over 5 MW)Wyoming Legislatureenacted 2019[3]
Large Power Contract Service (LPCS) tariffCheyenne Light retail servicein effect since 2016[5]
Microsoft land purchase, about 3,200 acres in southeast CheyenneCity of Cheyenneannounced Apr. 14, 2026[4]

Cheyenne Light, Fuel and Power says it is filing “out of an abundance of caution.” The filing, made with FERC on November 24 in Docket ER27-634, is three Facility Expansion Agreements with Microsoft [1]. The agreements cover new lines and substations for three Microsoft data center campuses in the utility’s Wyoming territory. Microsoft pays for all of it up front, and Cheyenne Light’s position is that FERC does not need to see any of it [1].

The filing is small. The question behind it is not: once FERC starts writing rules for large-load cost recovery agreements, how many utilities outside the organized markets will decide their retail data center contracts belong in a FERC docket too?

What Cheyenne Light put in ER27-634

Cheyenne Light is a Black Hills Corporation subsidiary with about 46,000 retail electric customers in and around Cheyenne [1]. It offers transmission service under its own open access tariff, with a formula rate in Attachment H-1, but recovers its transmission costs from retail customers through retail rates; any wholesale transmission revenue is credited back to them [1]. Microsoft is a retail customer [1].

According to the letter, Microsoft is developing three campuses in Cheyenne Light’s certificated service area and has asked for new retail delivery points, which will take distribution- and transmission-level construction [1]. The three agreements are:

  • Meadowlark Campus, Rate Schedule No. 13
  • Equality Campus, Rate Schedule No. 14
  • Frontier Campus, Rate Schedule No. 15 [1]

Each one has Microsoft fund the facilities through a series of contribution in aid of construction payments, or CIAC, meaning cash paid to the utility for plant it will own. “Due to the CIAC payments, the capital costs of the facilities will be booked on Cheyenne Light’s books as $0,” the letter says, so they will not flow through the transmission formula rate [1]. Microsoft also pays a negotiated construction fee and an operation and maintenance fee, and the O&M revenue is counted in state retail ratemaking [1].

The utility asks for a December 24 effective date, 30 days after filing, and a waiver of FERC’s 60-day notice rule so the agreements are in place before the first payments come due [1]. It also asks that FERC accept them “as submitted and without modification or condition” [1].

Why a retail contract is in a FERC docket

The letter is plain that the agreements exist for Wyoming’s purposes. They satisfy “Wyoming statutory and state retail tariff requirements which prohibit cost-shifting of large load costs to retail customers,” and they “do not provide any Commission jurisdictional service” [1].

The statute is W.S. 37-3-116, enacted in 2019. For customers with projected usage above 5 megawatts, served under a tariff the Wyoming PSC has approved, a utility’s service agreement must be expected to bring in more revenue than the cost to serve, and it “shall not result in obligating other customers for any utility investments or any direct, indirect or reasonably assigned costs” of serving that customer [3]. Profits or losses on such agreements stay with the utility’s owners, and the utility reports to the PSC at least every three years on the effect on other ratepayers [3].

The federal trigger is a single footnote. Cheyenne Light cites FERC’s order in PJM Interconnection, L.L.C., 195 FERC ¶ 61,211, which found PJM’s tariff unjust and unreasonable in part because it lacked a pro forma agreement for recovering network upgrade costs caused by large loads [1]. As this column noted on November 18, PJM’s transmission owners have since proposed a cost recovery agreement with a term of at least 10 years. Cheyenne Light is not in PJM. It filed anyway, and asked FERC to accept the agreements only “to the extent the Commission determines that the Agreements are subject to Commission oversight” [1].

What the public copy shows, and what it hides

The cost caps, facility cost estimates, payment schedules, Microsoft’s site coordinates and its load forecasts are all marked highly confidential [1]. So is most of Exhibit 1, which describes the facilities [2]. There is no megawatt figure anywhere in the public record of this docket.

What survives in the Meadowlark agreement is the risk allocation [2]:

  • Regulatory failure. If the Wyoming PSC denies or materially conditions the needed approval and the parties cannot agree on a fix, Microsoft reimburses the utility’s costs incurred or committed, up to a Facility Construction Cost Cap, and Cheyenne Light may terminate [2].
  • Credit. Cheyenne Light does not expect to need security given Microsoft’s creditworthiness, but a downgrade below investment grade triggers a letter of credit or cash deposit [2].
  • Ongoing costs. The utility owns and operates the facilities; Microsoft compensates it for the reasonable cost of continued operation and maintenance, and reimburses taxes and gross-ups tied to them [2].
  • Delay. A force majeure extension of the in-service date beyond 360 days gives Microsoft a right whose terms are redacted [2].

Construction cannot start until the Wyoming PSC grants a certificate of public convenience and necessity for each agreement’s facilities, and the agreements will be filed as support for those applications [1]. That makes Wyoming, not FERC, the venue where the facilities themselves get reviewed.

The letter also does not say where Meadowlark, Equality or Frontier sit. In April, Microsoft announced its intent to buy about 3,200 acres southeast of downtown Cheyenne, a 200-acre parcel in Bison Business Park and 3,000 acres next to it [4]. Whether any of the three campuses is on that land, the filing leaves unsaid.

Where the sides stand

Cheyenne Light and Microsoft describe one arrangement. Microsoft’s April release says its Large Power Contract Service tariff with Black Hills “requires Microsoft to directly pay for all the infrastructure upgrades and power procured by the utility necessary to serve its load” [4]. Wes Ashton, Black Hills Energy’s vice president of utilities in Wyoming and South Dakota, said in the same release that the tariff lets the utility meet Microsoft’s needs “while protecting base retail customers from rate impacts” [4].

Wyoming’s consumer advocate has said much the same, though about the tariff rather than these agreements. Anthony Ornelas, who leads the Office of the Consumer Advocate, told AARP Wyoming in December 2025: “I don’t see a scenario where residential or commercial customers are asked to pay higher rates for the capital investments or energy procured to serve data centers” [5]. He traced the Large Power Contract Service tariff, in place since 2016, to talks with Cheyenne Light over Microsoft’s first project, aimed partly at keeping stranded costs off other customers if Microsoft left [5]. The worry he did raise was indirect: that demand growth and coal retirements could push up natural gas prices [5].

Everyone else has not yet appeared. No intervention, comment or protest was on file in ER27-634 in the record this column draws on, and FERC had not noticed a comment date.

What I’m watching

First, whether FERC accepts the three agreements by December 24, rejects them, or says it lacks jurisdiction, which is the outcome Cheyenne Light’s own letter argues for [1]. Any of the three would tell other non-RTO utilities whether their retail data center contracts belong at FERC.

Second, the Wyoming PSC certificate filings for Meadowlark, Equality and Frontier [1]. Those dockets are where the facilities, and possibly some of the redacted numbers, will be examined.

Owen Hollis

Key dates

  • Cheyenne Light's requested effective date for the three Microsoft agreements (ER27-634)

What did Cheyenne Light file at FERC for Microsoft's data centers?

Three Facility Expansion Agreements, one each for Microsoft's Meadowlark, Equality and Frontier campuses, filed November 24, 2026 as Rate Schedule Nos. 13, 14 and 15 in Docket ER27-634 [1]. Cheyenne Light asked FERC to accept them effective December 24, 2026 [1].

Who pays for the power lines and substations serving Microsoft's new Cheyenne campuses?

Microsoft, through contributions in aid of construction, so the utility books the facilities' capital cost at $0 and does not collect it through its transmission formula rate [1]. Microsoft also pays a construction fee and operation and maintenance costs [1,2].

Does FERC have jurisdiction over Cheyenne Light's Microsoft agreements?

Cheyenne Light says the agreements provide no FERC-jurisdictional service and that it filed them only because of FERC's recent statements on large-load cost recovery agreements [1]. It asked FERC to accept them to the extent FERC finds they are subject to its oversight [1].

How much power will Microsoft's Meadowlark, Equality and Frontier campuses use?

The public filing does not say. Microsoft's load forecasts are among the items Cheyenne Light asked FERC to keep confidential [1].

Can Cheyenne Light start building the Microsoft facilities once FERC accepts the agreements?

No. Construction cannot begin until the Wyoming Public Service Commission issues a certificate of public convenience and necessity for each agreement's facilities [1,2].

Cheyenne Light filed the three agreements in public and privileged versions; the public copies redact Microsoft's site coordinates and load forecasts, the facility cost estimates and cost caps, and the construction and payment schedules, so this column gives no megawatt or dollar figure for the campuses. The Equality and Frontier agreements' public text matches the Meadowlark agreement in the passages quoted here. The filing does not say where the three campuses are, and this column does not assume any of them sits on the land Microsoft announced in April. W.S. 37-3-116 is quoted as enacted in 2019; this column does not address whether later sessions amended it. FERC had not issued a notice setting a comment date, and no party had intervened or protested, in the record this column draws on. The Wyoming PSC certificate applications the filing describes had not been identified by docket number in that record. The consumer advocate's remarks are from a December 2025 interview and predate these agreements.

  1. 1Filing of Load Facility Expansion Agreements and Request for Waiver (transmittal letter), Docket No. ER27-634-000Cheyenne Light, Fuel and Power Company · November 24, 2026 · elibrary.ferc.gov
  2. 2Attachment A, Clean Facility Expansion Agreement, Meadowlark Campus (public version), Docket No. ER27-634-000Cheyenne Light, Fuel and Power Company · November 24, 2026 · elibrary.ferc.gov
  3. 3Enrolled Act No. 102 (HB0113), creating W.S. 37-3-116, Electric utility service agreementsWyoming Legislature · 2019 General Session · wyoleg.gov
  4. 4Microsoft announces intent to expand datacenter operations in Cheyenne, accelerating innovation and economic growthMicrosoft · April 14, 2026 · news.microsoft.com
  5. 5Will Data Centers Mean Higher Power Costs in Wyoming?AARP Wyoming · December 11, 2025 · aarp.org

Filed under: Wyoming / Cheyenne Light / Black Hills Energy / Microsoft / cost allocation / transmission / data centers