PJM's Answer to FERC on Data Centers: One 12-Month Study for Load and Generation, but the First Cycle Ends in 2029

In FERC Docket ER27-531, PJM folds large-load service requests into a single yearly study it calls Fast Energization. The transmission owners' companion filing, ER27-520, sets the price of entry: a cost recovery agreement of at least 10 years and a walk-away payment that climbs to 100%.

Owen HollisLoad Factor News

Load Ledger
ItemBodyLoadStageSrc
Fast Energization Process, Interim NITS, Firm and Non-Firm Contract Demand services, 50 MW behind-the-meter netting limitFERC Docket ER27-531 (PJM)applies to Large Loads of 50 MW or morefiled Nov. 16, 2026; most provisions requested effective Mar. 16, 2027; study process effective date indefinite[1]
Cost Recovery Agreement, Interconnection Reliability Reinforcement Charge, rates for new servicesFERC Docket ER27-520 (PJM Transmission Owners)—filed Nov. 16, 2026[2]
Ride-through and operational requirements for Large Computational LoadFERC Docket ER27-522 (PJM)—filed Nov. 16, 2026; effective date requested Jan. 16, 2027[3]
Large Load Show Cause proceedingFERC Docket EL26-67—PJM asks FERC to close the section 206 portion[1]

PJM told FERC on Monday that its new study for data centers and power plants “should be twice as fast as the current process” [1]. By PJM’s own schedule, the first data center to go through it would get its answer in 2029 [1]. Both statements are in FERC Docket ER27-531, PJM’s response to the June 18 large-load show cause order, filed with a transmission owners’ cost package in ER27-520 and a ride-through filing in ER27-522 [1,2,3]. PJM asks FERC to treat the set as a full answer and close the section 206 part of the case [1].

Why PJM says it needs a new process

PJM’s 2026 load forecast projects summer peak growing 3.6% a year over the next decade; in 2023 it projected 0.8% [1]. Its 2025 forecast put peak growth at 32 GW from 2024 to 2030, 30 GW of it from data centers [1]. Data centers can be built in 12 to 18 months, PJM notes, faster than the plants and lines that serve them [1].

The operational side is in ER27-522. On July 22, 2026, PJM says, an event involving about 3.9 GW of large load pushed Eastern Interconnection frequency to 60.092 Hz [3]. PJM wants ride-through rules for Large Computational Load effective January 16, 2027 [3].

What PJM filed

  • A registry baseline. All Large Load, meaning 50 MW or more at one site, must be on PJM’s registry by March 1, 2027 [1]. That sets the existing level of network service; any growth beyond it requires an application and a study [1]. Today the tariff sets no limit on a network customer’s load growth [1].
  • One study for load and generation. Fast Energization replaces three system impact studies with a screening phase of about four months, two “turns” each under 60 days with non-binding cost and schedule estimates, then one system impact study [1]. Applicants post readiness deposits up front, and no physical change to a project or load is allowed after the application; a change means withdrawing and waiting a year [1]. PJM reports that only 5% of applications it now receives are correct and complete on first submission [1].
  • Three services. Interim NITS is energy-only and interruptible while upgrades are built [1]. Firm Contract Demand service carries energy and capacity to a set megawatt level; Non-Firm Contract Demand is as-available [1]. A load that took firm service cannot switch that portion to non-firm for five years, and ending firm service takes 42 months’ notice [1]. A site served entirely by co-located generation must still sign a service agreement for zero MW [1].
  • Penalties that bite. One misoperation of a load’s control or protection scheme suspends service for up to 120 days; a second terminates the agreement [1].
  • A 50 MW netting cap. From March 16, 2027, a customer may net no more than 50 MW of retail behind-the-meter generation from its load, with exemptions for arrangements existing on December 18, 2025, a three-year transition and qualifying cogeneration [1].

The timing is the catch. Fast Energization cannot start until Cycle 01 of PJM’s current process clears its second decision point, which PJM expects in late November 2027 [1]. Then comes an early May 2028 soft close, 14 weeks of application coaching, an August 2028 deadline and a first cycle that ends in 2029 [1]. Pending Cycle 02 applications would be resubmitted into the new process [1]. In the meantime, loads use the Necessary Studies process FERC already directed [1].

Who pays: the transmission owners’ half

PJM does not set cost allocation. The transmission owners hold those filing rights, and they used them in ER27-520 [1,2]. Their package has four parts [2].

  1. A cost recovery agreement before the study. The customer serving a large load must sign it, or a comparable agreement accepted by FERC, to enter Fast Energization [2]. The term is at least 10 years, negotiated case by case [2]. Credit support starts at 100% of the projected charges for the initial load commitment over the full term and declines as obligations are met [2].
  2. A minimum, not a cost. Once service starts, the customer owes a Minimum Commitment Percentage of 80% to 100% of a Full Firm Transmission Service Benchmark, set by each owner [2]. Actual transmission revenue counts against it; only the shortfall is billed [2].
  3. A walk-away price that climbs. Early termination costs a share of the present value of the remaining commitment: 25% before the final PJM agreement, 50% in the 180 days after it, 75% until service starts, 100% after [2]. Delays the customer did not cause do not push it into a higher tier [2].
  4. Zones, then the region. Upgrades from each cycle, which PJM calls Interconnection Reliability Reinforcements, go only to zones with large loads in that cycle, by proportional impact, through a new charge that lasts 15 years [2]. Generators in the cycle pay a 15-year fee credited back to those zones [2]. After year 15, what remains moves to regional allocation under Schedule 12 [2].

The owners also price non-firm service below firm by the zone’s load factor. Their simplified example takes a $90,000/MW-year firm rate in a zone with a 64.7% load factor to about $58,219/MW-year, a 35.3% discount [2]. They commit to formula-rate protections for municipal utilities and cooperatives on compliance, without numbers yet [2].

Readers of yesterday’s column on MISO’s version will recognize the shape: a minimum measured against what the load would have paid anyway, with shortfalls billed.

Where the sides stand

The Joint Consumer Advocates, made up of the Maryland Office of People’s Counsel, the Ohio Consumers’ Counsel, the Delaware Division of the Public Advocate and the Illinois Attorney General, set their test in July [4]. A minimum keyed to service level and the full cost of upgrades part ways whenever upgrade costs exceed the network charges attributable to the load, “which they will do, routinely and significantly,” they wrote [4]. Their standard: an agreement is just and reasonable “only if it requires the Eligible Customer to pay the full cost of the Network Upgrades” [4]. They also asked that payments be credited to other customers in the same zone immediately [4]. The owners’ 80% floor and year-16 handoff are where that test will be applied.

Developers of flexible load want speed. Calibrant Energy and Camus Energy told PJM in September that even a best-case 12 months “falls short” of FERC’s suggestion of studies on the order of 60 to 90 days [5]. They asked for exit points for flexible loads before a cycle ends [5].

Generators worry about the company they will keep. The American Clean Power Association said folding large loads into generator clusters “reintroduces exactly the heterogeneity” PJM’s 2022 reforms removed, and that “A November filing remains premature” [5]. It put PJM’s then-proposed readiness deposits at roughly $4.1 million by the second decision point for a 100 MW project [5]. Constellation asked that paired plants and loads not be costed “as though the generating resource and load were seeking full, independent deliverability rights” [5].

Large buyers, through the Corporate Energy Buyers Association, backed the 90-day pause that produced these filings, warning against “a rushed proposal that would unnecessarily shift stakeholder debate to the Commission docket” [6]. Its members now have the filings it asked for.

PJM, for its part, says full acceptance within 10 months is likely needed to run Cycle 02 under the new rules, and asks for an order within 120 days [1].

What I’m watching

  • Comment date. PJM asked for 60 days [1]. Its stakeholder sessions run November 23 and December 15 [1]. Watch whether the consumer advocates press the full-cost standard against the 80% floor [2,4].
  • March 16, 2027: the effective date PJM requests for the services and the netting cap [1]. PJM has also asked for more abeyance so it can file revised interconnection agreements and a security form later [1].

Whether a data center that signs a 10-year agreement in 2028 is still paying anything for its upgrades in year 16 is the question ER27-520 answers with a handoff to the region [2]. The consumer advocates asked for a different answer before this filing existed [4].

Owen Hollis

Key dates

  • PJM stakeholder session on the filings
  • PJM stakeholder session on the filings
  • Effective date PJM requests for ride-through requirements (ER27-522)
  • All PJM Large Load due on the Large Load Registry
  • Effective date PJM requests for new services, NITS changes and netting limit (ER27-531)

What is PJM's Fast Energization Process?

It is a proposed single, roughly 12-month study that would take generator interconnection requests and transmission service requests for large loads together, in one yearly cluster [1]. PJM says it would take half the time of its current cycle process [1].

When would a data center first be studied under Fast Energization?

PJM expects the first submission window to open in late November 2027, with an application deadline in August 2028 and the first cycle finishing in 2029 [1]. Until then, co-located and other eligible loads go through PJM's Necessary Studies process [1].

What does the PJM transmission owners' cost recovery agreement require of a large load?

The customer must sign it before entering PJM's study, for a term of at least 10 years, and post credit support equal to 100% of the projected charges for its initial load commitment [2]. Once service starts, it owes a minimum of 80% to 100% of a full firm-service benchmark each period, with any shortfall billed [2].

How much does a data center owe if it walks away from a PJM cost recovery agreement?

Under the transmission owners' proposal, the early termination amount is a percentage of the present value of remaining committed contributions: 25% before the final PJM agreement, 50% in the 180 days after it, 75% until service starts and 100% after that [2].

Who pays for transmission upgrades built for data centers in PJM under the new proposal?

For 15 years after a reinforcement enters service, its cost goes only to zones with large loads in that study cycle, by proportional impact, with generators paying a separate 15-year fee that is credited back [2]. After 15 years, the remaining cost moves to PJM's regional allocation under Schedule 12 [2].

This column draws on the transmittal letters for PJM's and the PJM Transmission Owners' November 16 filings and PJM's companion ride-through filing; it does not draw on the redlined tariff sheets, the pro forma Cost Recovery Agreement text, or the declarations and testimony attached to them. The non-firm rate figures are the transmission owners' simplified example for a hypothetical zone, not a rate for any real zone. The positions of the American Clean Power Association, Calibrant Energy and Camus Energy, and Constellation were given in PJM's September 16 workshop feedback poll, and the Joint Consumer Advocates' position comes from their July rehearing request on FERC's June 18 order; none had filed comments on ER27-531 or ER27-520 in the record this column draws on. The readiness deposit figures attributed to the American Clean Power Association describe PJM's September workshop design as that group summarized it, and may not match the filed tariff. FERC had not issued a notice setting a comment date for either filing; PJM asked for a 60-day comment period. The late-2027 and 2028 milestones are PJM's expectations and depend on the progress of its current interconnection cycle. Neither filing states a megawatt figure for any specific data center.

  1. 1Proposed Tariff Revisions for Large Loads and Additional Compliance with Co-Location Order and Request for Extended 60-Day Comment Period (transmittal letter), Docket No. ER27-531-000PJM Interconnection, L.L.C. · November 16, 2026 · elibrary.ferc.gov
  2. 2Proposed Revisions to the PJM Open Access Transmission Tariff Addressing Transmission Service, Cost Allocation, and Cost Recovery for Large Loads and Co-Located Loads (transmittal letter), Docket No. ER27-520-000PJM Transmission Owners · November 16, 2026 · elibrary.ferc.gov
  3. 3Operational Requirements for Large Computational Load and Annual Reporting (transmittal letter), Docket No. ER27-522-000PJM Interconnection, L.L.C. · November 16, 2026 · elibrary.ferc.gov
  4. 4Request for Rehearing and Clarification of the Joint Consumer Advocates, Docket No. EL26-67Maryland Office of People's Counsel · July 17, 2026 · elibrary.ferc.gov
  5. 5September 16 Co-Located Load Order Workshop Stakeholder Feedback Poll ResponsesPJM Interconnection, L.L.C. · September 2026 · pjm.com
  6. 6Answer of Corporate Energy Buyers Association in Support of the Motions for Abeyance, Docket No. EL26-67-000Corporate Energy Buyers Association · August 7, 2026 · elibrary.ferc.gov

Filed under: large load interconnection / cost allocation / transmission / data centers / co-location / non-firm service