SWEPCO Asks FERC to Bill Its Wholesale Customers on Winter Peaks; the Co-op Facing a 207.9% Increase Points to North Louisiana Data Centers
In Docket ER27-369, SWEPCO wants to replace a summer-only demand charge with one keyed to its four highest monthly peaks in any season. East Texas Electric Cooperative says the filing ignores the load actually driving SWEPCO's capacity needs.
| Item | Body | Load | Stage | Src |
|---|---|---|---|---|
| SWEPCO Annual 4-CP demand charge, Rate Schedules 119, 125, 126, 127, 129 | FERC Docket ER27-369 | — | filed Oct. 30, 2026; requested effective Jan. 1, 2027 | [1] |
| ETEC protest and motions to reject, deny waivers or suspend | FERC Docket ER27-369 | — | filed Nov. 20, 2026 | [2] |
| Large-load electric service agreements, three north Louisiana data center campuses | SWEPCO retail service (Louisiana) | — | signed; size confidential in Arkansas PSC Docket 26-056-U | [3] |
| Brantley Branch battery storage acquisition | Arkansas PSC Docket 26-056-U | 200 MW | pending | [3] |
In Arkansas, SWEPCO has testified that summer peaks are the right basis for dividing up its generation costs. At FERC, in a filing dated October 30, it asks for the opposite for five wholesale customers: bill them on the four highest monthly peaks of the year, whatever the season [1,2]. The customer that would pay for the change, East Texas Electric Cooperative, filed a protest on November 20 arguing that the winter capacity SWEPCO is now buying traces to new data center load in north Louisiana, not to the co-op [2].
This is a wholesale rate case, not a large-load tariff. It belongs in this column because it shows a cost question this column has mostly seen from the other side: when a utility’s capacity need grows, which existing customers’ bills move first.
What SWEPCO filed in ER27-369
Southwestern Electric Power Company, an AEP subsidiary serving about 560,000 customers in Louisiana, Texas and Arkansas, sells requirements power under five FERC rate schedules: Nos. 119 and 129 to ETEC (No. 119 came over when Northeast Texas Electric Cooperative merged into ETEC on June 1, 2026), No. 125 to Hope Water and Light, No. 126 to Bentonville and No. 127 to Prescott [1]. Each contract sets a monthly demand charge from a cost-of-service formula. Today that charge uses the average of the four highest hourly system demands in June through September, the “Summer-only 4-CP” [1].
SWEPCO would replace it with the four highest monthly coincident peaks of the contract year, summer or winter [1]. Rate Schedule No. 129’s 80 MW minimum purchase would be recalculated on the same annual basis [1]. FERC noticed the filing with a January 1, 2027 effective date and a November 20 comment deadline [4].
The stated reason is SPP’s resource adequacy program. SPP’s summer planning reserve margin went to 16% for summer 2026; the winter margin starts at 36% for winter 2026/2027, rising to 17% and 38% by 2029/2030 [1]. “Because SPP’s winter PRM is significantly larger than its summer PRM, the winter season now drives SWEPCO’s capacity needs,” the transmittal letter says [1].
Who pays: one customer, $26.6 million a year
SWEPCO’s own table, on 2025 data, is lopsided [1]:
- Hope: about $8.2 million to $7.5 million, down about 8.4%.
- Bentonville: about $26.5 million to $24.4 million, down about 7.8%.
- Prescott: about $2.0 million to $1.8 million, down about 10.2%.
- ETEC, Rate Schedule No. 119: about $19.2 million to $18.2 million, down about 5.2%.
- ETEC, Rate Schedule No. 129: about $12.8 million to $39.4 million, up about $26.6 million, or 207.9%.
SWEPCO reads the size of that jump as proof of its case: it “demonstrates that ETEC imposes both substantial summer and winter capacity costs” that the summer method misses, costs that would otherwise fall on other wholesale customers [1]. ETEC reads the same numbers differently. By its count from SWEPCO’s Attachment D, the five customers’ billing demand would go from 413.2 MW of a 3,868.5 MW system peak (10.7%) to 586.8 MW of 4,082.5 MW (14.4%), and SWEPCO’s net wholesale revenue would rise about $22.6 million a year [2]. Held flat to the contract’s March 31, 2031 end, ETEC puts its own added cost at about $108.7 million [2].
Where the data centers come in
SWEPCO’s FERC filing never mentions data centers [1]. Its Arkansas testimony does.
In Arkansas PSC Docket 26-056-U, where SWEPCO seeks approval to buy the 200 MW Brantley Branch battery project in Rusk County, Texas, resource planning director James F. Martin testified September 8 that SWEPCO “has signed new large load Contracts for Electric Service (ESA) across three data center campuses in north Louisiana” [3]. That load “is expected to begin adding to the Company’s need for capacity as early as the upcoming SPP’s 2027/2028 winter resource adequacy season,” and the customers should run “between 93 and 98.5 percent of their maximum load during SWEPCO’s peak hours” [3]. Excluding large data centers, Martin forecast about 300 MW of cumulative growth by 2030, roughly 1% a year [3]. The data center megawatts and ramp schedule sit in a confidential exhibit [3].
Martin’s testimony also helps SWEPCO’s side. He calls winter “the season with the greatest need for SWEPCO,” and his capacity charts fold the new contracted load into the obligation [3].
Where the sides stand
SWEPCO says FERC precedent allows a utility to revise an allocation method after “supervening changes,” and that SPP’s separate winter margin is one [1]. It reports 2021-2025 peak-load test results of 19% on the On and Off Peak Test and 81% on the Average to Annual Peak Test, both at FERC’s thresholds, and 62% on the Low to Annual Peak Test, short of the 66% mark [1]. Winter equaled the annual peak in three of those five years, it says [1].
ETEC says those results are rounded to the line: 18.999% and 81.065% in SWEPCO’s own data, and 19.013% on FERC Form 1 data, which would favor summer [2]. Its bigger argument is consistency. SWEPCO defended summer 4-CP in its Arkansas rate case approved January 24, 2026, and in Texas rebuttal testimony in PUCT Docket 58819 it declined to add January 2025 as a peak; in Texas discovery, SWEPCO witnesses said weather-normalized peaks “consistently occur during the summer season” [2]. ETEC also notes SWEPCO signed the White House Ratepayer Protection Pledge in July and argues existing customers should not see increases “predicated on load growth that is not attributable to those customers” [2]. It asks FERC to reject the filing, deny SWEPCO’s blanket waiver of cost-support rules, or suspend the rates five months subject to refund and send them to hearing and a settlement judge [2].
The Louisiana PSC, whose jurisdiction holds the data center campuses, intervened November 19 without stating a position [5]. Hope, Bentonville and Prescott, whose bills would fall under the proposal [1], have no filing in the docket in the record this column draws on.
What I’m watching
SWEPCO’s answer to the protest, and whether it addresses the Louisiana contracts at all. Then FERC’s order before the requested January 1, 2027 date: accept, suspend for five months, or reject [1,2].
The question underneath is one FERC’s rules do not answer directly. If a utility’s winter peak is rising because of new retail data center load, should the formula for an existing wholesale customer change before that load arrives, or after anyone can see it?
Owen Hollis
Key dates
- SWEPCO's requested effective date for the Annual 4-CP demand charge (ER27-369)
- Termination date of ETEC's Rate Schedule No. 129 after the 2025 extension
Reader questions
What is SWEPCO asking FERC to change in its wholesale power contracts?
SWEPCO wants the demand charge in five wholesale contracts to be based on its four highest monthly system peaks in any season, instead of the four summer months of June through September [1]. It asked for the change to take effect January 1, 2027 [1,4].
How much would East Texas Electric Cooperative's rates go up under SWEPCO's proposal?
By SWEPCO's own figures from 2025 data, the demand charge under Rate Schedule No. 129 would rise from about $12.8 million to about $39.4 million a year, an increase of about 207.9% [1]. ETEC calculates about $108.7 million through the contract's March 31, 2031 end [2].
Which SWEPCO wholesale customers would pay less?
Hope Water and Light (about 8.4% lower), Bentonville (about 7.8%), Prescott (about 10.2%) and ETEC's Rate Schedule No. 119 (about 5.2%), according to SWEPCO [1].
What do data centers have to do with SWEPCO's wholesale rate filing?
SWEPCO's filing does not mention them [1]. ETEC's protest points to SWEPCO's Arkansas testimony that it has signed contracts with three north Louisiana data center campuses whose load could add to its capacity need as early as the 2027/2028 SPP winter season [2,3].
A note on sourcing
This column draws on SWEPCO's transmittal letter and on ETEC's protest, not on the Duffy affidavit or the rate attachments filed with SWEPCO's application. The 413.2 MW and 586.8 MW billing-demand figures, the $108.7 million figure over the remaining contract term and the $22.6 million net revenue figure are ETEC's calculations from SWEPCO's Attachment D and have not been checked against a SWEPCO calculation. SWEPCO had not answered the protest in the FERC record as of publication. The size and ramp schedule of the north Louisiana data center contracts are confidential in the Arkansas proceeding, and neither SWEPCO's FERC filing nor any public document this column draws on gives a megawatt figure for them. Hope, Bentonville and Prescott, whose rates would fall, had filed nothing in the FERC docket in the record this column draws on. The Louisiana PSC's intervention states no position. FERC has not acted on the filing.
Sources
- 1Amended Power Supply Agreements Nos. 119, 125, 126, 127 and 129, Transmittal Letter, Docket No. ER27-369-000Southwestern Electric Power Company · October 30, 2026 · elibrary.ferc.gov
- 2Protest, Motion to Deny Waivers, Motion to Reject Filing, or in the Alternative, Request for Maximum Suspension, Hearing, and Appointment of Settlement Judge of East Texas Electric Cooperative, Inc., Docket No. ER27-369-000East Texas Electric Cooperative, Inc. · November 20, 2026 · elibrary.ferc.gov
- 3Direct Testimony of James F. Martin on Behalf of Southwestern Electric Power Company, Arkansas PSC Docket No. 26-056-USouthwestern Electric Power Company · September 8, 2026 · apps.apsc.arkansas.gov
- 4Combined Notice of Filings #2 (including Docket No. ER27-369-000)Federal Energy Regulatory Commission · October 30, 2026 · elibrary.ferc.gov
- 5Notice of Intervention of the Louisiana Public Service Commission, Docket No. ER27-369-000Louisiana Public Service Commission · November 19, 2026 · elibrary.ferc.gov
Filed under: SWEPCO / cost allocation / wholesale rates / data centers / Louisiana / Arkansas