Data Center Coalition Asks FERC to Send NERC's Data Center Registry Back; Public Power Wants It Approved as Filed
Comments in FERC Docket RR27-1 split four ways: DCC wants a remand and a 75 MW threshold, QTS wants approval with rewritten definitions, EdgeConneX wants rejection, and public power and PJM back NERC's 50 MW, 100 kV criteria. Customer groups question whether end users belong in the registry at all.
| Item | Body | Load | Stage | Src |
|---|---|---|---|---|
| Computational Load Owner and Operator registry criteria (Rules of Procedure Appendices 2, 5A, 5B) | FERC Docket RR27-1 (NERC) | 50 MW or more at 100 kV or above | comments closed Nov. 20, 2026; pending | [1] |
| Request to remand and raise the threshold | Data Center Coalition, RR27-1 | 75 MW | filed Nov. 20, 2026 | [2] |
| Request to approve with compliance filing on definitions | QTS Data Centers, RR27-1 | — | filed Nov. 20, 2026 | [3] |
| Request to reject the registry revisions | EdgeConneX, RR27-1 | — | filed Nov. 20, 2026 | [8] |
| Support for approval as filed | APPA, LPPC and TAPS; PJM, RR27-1 | — | filed Nov. 20, 2026 | [4] |
| Request to deny expedited action and hold further proceedings | Electricity Customer Alliance, RR27-1 | — | filed Nov. 20, 2026 | [5] |
The Data Center Coalition asked FERC on November 20 to send NERC’s data center registration rules back to NERC [2]. The trade group’s members would be the ones registering. Public power utilities, filing the same day in Docket RR27-1, asked FERC to approve the rules as filed [4].
Those two filings bracket the record. Between them sit data center operators who disagree with each other, PJM, and large-customer groups asking whether end users belong in NERC’s registry at all [3,5,6,7,8]. QTS, one of the operators, says it expects to register under whatever criteria FERC approves [3].
What NERC asked FERC to approve
NERC’s October 21 petition would add two registered entity types to its Rules of Procedure: the Computational Load Owner, “the entity that owns and maintains a Computational Load Site,” and the Computational Load Operator, “the entity that operates a Computational Load Site” [1,2]. A Computational Load Site is one or more buildings, structures or installations “at a single location” that primarily contain IT infrastructure for software services, AI training and deployment, cryptocurrency mining or other data center computing, and that are supplied through equipment connected to the bulk-power system [1].
Registration applies at 50 MW or more of total connected load, supplied through equipment connected at 100 kV or above [1]. NERC started at 20 MW and 60 kV in its April draft and raised both after comments [1]. Its dataset counted 41,827 MW of active data center load as of June 2026 and 37,675 MW more under construction for service by the end of 2027, about 79,502 MW in all; the final thresholds cover about 86% of that [1]. NERC asked for expedited action so Regional Entities can begin outreach before the standards take effect [1].
As this column noted on November 23, those standards are in a separate docket, RD27-3. Comments there are due December 17 [9].
Where the data center filings part ways
Three data center filings, three different requests.
DCC: remand. The coalition’s lead argument is jurisdiction. Section 215 of the Federal Power Act reaches “users, owners, and operators of the bulk-power system,” and DCC says a retail customer that does not directly receive, sell, buy or transmit power over that system is not a user [2]. NERC measures voltage at the high side of whatever equipment feeds the site, “irrespective of electrical equipment ownership,” so DCC offers this example: a data center taking retail service at 34.5 kV could be registered because the utility’s distribution equipment ties into a 115 kV line [2]. “But impact is not use,” the brief says [2].
DCC’s second argument is the threshold. By its reading of NERC’s technical attachment, a 75 MW line would still cover about 63,960 MW, or 80% of current and forecast computational load, against 68,288 MW, or 86%, at 50 MW [2]. The difference is about 4.3 GW nationwide, and DCC notes NERC can still register a smaller site through its material-impact process [2]. NERC’s response, quoted by DCC, was that 75 MW would drop sites “similar in size” to those that have shown “unforeseen and difficult-to-explain dynamic behaviors” [2].
The third argument is timing. NERC took nearly three years, May 2023 to May 2026, to register inverter-based resources, DCC says, so most computational loads may not be registered when the CLO standards start applying, which DCC puts as early as the end of 2027 or early 2028 [2].
QTS: approve, then fix the text. QTS, a DCC member, says NERC “built the registration criteria on a sound structure” [3]. Its campuses are mostly multi-tenant: QTS owns the substation where it has one and the campus distribution, and each tenant controls only its own workloads [3]. NERC’s interpretations live in a Consideration of Comments attachment that does not bind Regional Entities, QTS argues, so it wants FERC to order a compliance filing with new text [3]. The operator, under its wording, would be “the entity that controls the electrical demand of the site,” and the owner would be the entity that “owns and maintains the electrical infrastructure” [3]. Read literally, QTS says, NERC’s owner definition “could reach hundreds of tenants at a single campus” [3].
EdgeConneX: reject. EdgeConneX, which operates data centers in 26 U.S. cities, asks FERC to reject the revisions as uncertain and as imposing obligations on entities that do not control the relevant equipment [8].
Who carries the compliance cost, and who is left out
Registration is where the cost starts. Registered entities would owe the CLO standards’ modeling-data, operating-instruction and disturbance-monitoring duties [2,3,5]. DCC calls the 50 MW line an “unnecessary” compliance cost on loads and “the customers that they serve” [2]. On location, NERC’s “single location” test aggregates buildings by ownership, shared cooling or coordinated computing, not parcel lines [2,3]. DCC says that leaves a phased campus, with buildings across a road energized years apart, open to different answers in different regions [2].
Large customers outside the data center business want a clean line drawn. ELCON, the large industrial group, credits NERC for stating that “load that is more industrial or primarily manufacturing is excluded” and asks FERC to keep factory automation and enterprise IT out [6].
Where the other sides stand
APPA, the Large Public Power Council and TAPS want approval, and they want FERC to say approval decides nothing broader about “the scope of the bulk-power system and its users” [4]. PJM is “very supportive” and asks FERC to push NERC’s registry to share data with the RTO and state large-load registries so there are not “a multitude of different types of registries” across an interconnection [7]. PJM also notes the NERC registry reaches only loads that have reached commercial operation, while planners need projected load [7].
The Electricity Customer Alliance, whose members range from technology companies to residential ratepayer advocates, asks FERC to deny expedited treatment [5]. Its question is whether end-use customers, which do not plan or operate the grid, belong in the reliability framework at all, or whether standards on existing registered utilities, enforced through interconnection agreements, would work better [5]. It also suggests revisiting registration of load-serving entities, which NERC dropped in 2015 [5]. ELCON shares the jurisdiction concern while backing NERC’s manufacturing exclusion [6].
What I’m watching
First, NERC’s answer, and whether it gives up anything on the operator and owner definitions that QTS and DCC both attack. Second, the December 17 comments in RD27-3, which will show whether the same parties fight the standards as hard as the registry [9]. The record now offers FERC three paths: approve with directives (QTS), remand (DCC) or reject (EdgeConneX). NERC asked for expedited action and named no date [1].
Owen Hollis
Key dates
- Comments due on NERC's computational load standards CLO-001, CLO-002 and CLO-003 (RD27-3)
Reader questions
What did the Data Center Coalition ask FERC to do with NERC's computational load registry?
Remand it to NERC [2]. DCC argues the criteria reach retail customers that Section 215 of the Federal Power Act does not cover, leave unclear which entity at a data center must register, and should use a 75 MW threshold instead of 50 MW [2].
Which data centers would have to register with NERC?
Under NERC's proposal, the owner and operator of any Computational Load Site with total connected load of 50 MW or more, supplied through equipment connected at 100 kV or higher from one or more points of connection [1]. NERC says those thresholds capture about 86% of the computational load it projects by the end of 2027 [1].
Who registers at a multi-tenant colocation data center under the NERC rules?
The petition does not settle it; NERC's definitions name whoever operates, or owns and maintains, the site, and leave divided structures to case-by-case review [1]. QTS asks FERC to make the operator the entity that controls the site's electrical demand and the owner the entity that owns and maintains its electrical infrastructure [3].
Do utilities support registering data centers with NERC?
The public power groups APPA, LPPC and TAPS asked FERC to approve the criteria, and PJM said it is very supportive [4,7]. Both asked FERC to add limits or guidance in its order rather than change the criteria [4,7].
When could data centers face NERC compliance deadlines?
DCC says compliance with the related CLO standards could be required as early as the end of 2027 or early 2028, possibly before Regional Entities finish deciding who must register [2]. Comments on those standards, in Docket RD27-3, are due December 17, 2026 [9].
A note on sourcing
This column draws on the main body of NERC's October 21 petition and on seven of the comments filed by the November 20 comment date; it does not draw on the petition's technical attachments. The 68,288 MW and 63,960 MW figures for the 50 MW and 75 MW thresholds, and the roughly 4.3 GW difference between them, are the Data Center Coalition's reading of NERC's Attachment 1-E and have not been checked against that attachment here. NERC's 79,502 MW total and its 86% share come from a third-party data center tracking dataset NERC used, and cover load NERC expects in service by the end of 2027, not built load. Microsoft, North Country Data Center and several utilities intervened without filing comments. NERC had not answered the comments, and FERC had not acted on the petition or on NERC's request for expedited action, in the record this column draws on. No state commission or state consumer advocate had filed comments in RR27-1 in that record.
Sources
- 1Petition of the North American Electric Reliability Corporation for Approval of Revisions to the NERC Rules of Procedure Regarding Computational Load and Request for Expedited Action, Docket No. RR27-1-000North American Electric Reliability Corporation · October 21, 2026 · elibrary.ferc.gov
- 2Motion to Intervene and Comments of the Data Center Coalition, Docket No. RR27-1-000Data Center Coalition · November 20, 2026 · elibrary.ferc.gov
- 3Motion to Intervene and Comments of QTS Data Centers, Docket No. RR27-1-000QTS Data Centers · November 20, 2026 · elibrary.ferc.gov
- 4Motion to Intervene and Comments of the American Public Power Association, Large Public Power Council, and Transmission Access Policy Study Group, Docket No. RR27-1-000American Public Power Association · November 20, 2026 · elibrary.ferc.gov
- 5Comments and Request for Additional Proceedings of Electricity Customer Alliance, Docket No. RR27-1-000Electricity Customer Alliance · November 20, 2026 · elibrary.ferc.gov
- 6Motion to Intervene and Comments of the Electricity Consumers Resource Council, Docket No. RR27-1-000Electricity Consumers Resource Council · November 20, 2026 · elibrary.ferc.gov
- 7Comments of PJM Interconnection, L.L.C., Docket No. RR27-1-000PJM Interconnection · November 20, 2026 · elibrary.ferc.gov
- 8Motion to Intervene and Comments of EdgeConneX, Inc., Docket No. RR27-1-000EdgeConneX, Inc. · November 20, 2026 · elibrary.ferc.gov
- 9Combined Notice of Filings #1 (including Docket No. RD27-3-000)Federal Energy Regulatory Commission · November 17, 2026 · elibrary.ferc.gov
Filed under: NERC / reliability standards / data centers / computational load / registration / Data Center Coalition / public power