NERC Asks FERC to Put Data Centers Under Mandatory Reliability Standards: 50 MW, 100 kV, and an Open Question About Tenants

In Docket RD27-3, NERC filed three standards that would make large data center owners and operators answer to grid operators for models, data and operating instructions. A developer's objection in the companion registration docket asks who that owner actually is.

Owen HollisLoad Factor News

Load Ledger
ItemBodyLoadStageSrc
Reliability Standards CLO-001-1, CLO-002-1, CLO-003-1 and revised FAC-001-5, FAC-002-5FERC Docket RD27-3 (NERC)50 MW or more at 100 kV or abovefiled Nov. 17, 2026; comments due Dec. 17[1]
Registry criteria for Computational Load Owner and Computational Load Operator (Rules of Procedure Appendices 2, 5A, 5B)FERC Docket RR27-1 (NERC)50 MW or more at 100 kV or abovefiled Oct. 21, 2026; comment date passed Nov. 20; pending[2]
EdgeConneX request that FERC reject the registry revisionsFERC Docket RR27-1—filed Nov. 20, 2026[5]

About 3,900 MW of computational load dropped off the grid in a single event in July 2026, by NERC’s preliminary estimate, and system voltage spiked [1]. NERC put that figure in the petition it filed at FERC on November 17, Docket RD27-3, asking for the first mandatory reliability standards written for data centers themselves [1]. The three standards would reach owners and operators of sites of 50 MW or more connected at 100 kV or above [1]. Comments are due December 17 [3].

This is the federal reliability layer, separate from the tariff filings this column has spent the past week on. Those set who pays for upgrades. These set what a data center must tell the grid and what it must do when the grid tells it something.

What NERC filed, and on whose order

FERC’s July 16, 2026 order in Docket RD26-7 told NERC to file computational load standards by December 31, 2026, along with registration rules, and to file a workplan for later phases by March 1, 2027 [1]. NERC sent the registration half first: on October 21 it asked FERC, in Docket RR27-1, to add two new registered entity types, the Computational Load Owner and the Computational Load Operator [2]. FERC set November 20 as the comment date in that docket [4].

The November filing supplies the obligations those entities would carry. NERC’s Board adopted them October 26 [1]. On industry ballots they drew 78% to 98% approval initially and 78% to 95% on the final ballot [1].

A “Computational Load Site” is one or more buildings at a single location that primarily house IT equipment for software services, AI training and delivery, cryptocurrency mining or other data center computing, and is supplied from the bulk power system [2]. Registration applies only at the 50 MW and 100 kV line. NERC says that captures about 86% of all the computational load it projects by the end of 2027, at any size or voltage [2]. NERC calls this the first time it would “regulate certain large customers based on their impact on the reliable operation of the BPS” [2].

What the three standards require

  • CLO-001-1, interconnection, studies and modeling. Transmission Owners, Distribution Providers and Generator Owners must document interconnection requirements for these sites, including procedures for coordinated studies and commissioning [1]. The Generator Owner piece covers data centers co-located at a power plant [1]. A utility with no such site yet must publish its requirements within 45 days of signing a study agreement [1]. Planners set modeling data requirements, including ride-through and tripping settings and the expected use of the IT equipment, and the site owner must supply that data and verify it [1,5].
  • CLO-002-1, operational data and communications. Grid operators get the real-time data they specify, and each Computational Load Operator must comply with Operating Instructions from its Transmission Operator, Balancing Authority or Reliability Coordinator unless the action cannot be physically done or would breach safety, equipment, regulatory or statutory requirements [1,5]. NERC rewrites the glossary definition of Operating Instruction to include a command to a Computational Load Site [1].
  • CLO-003-1, protection and disturbance monitoring. High-resolution monitoring at the site and coordinated protection settings [1].

The standards do not set ride-through performance, meaning how long a load must stay connected through a voltage dip. NERC assigned that to a second project, 2026-03 [1]. PJM is writing its own rules in the meantime; its ride-through filing in ER27-522 was part of this column’s November 18 reading.

How long a data center has to comply

The standards would take effect on the first day of the first calendar quarter after FERC’s approval order takes effect [1]. From there, requirements phase in [1]:

  1. CLO-001-1: modeling and “qualified change” items at 3 months, interconnection requirements at 6, studies and data verification at 9.
  2. CLO-002-1: data specifications at 6 months; data delivery, Operating Instructions and communications at 12.
  3. CLO-003-1: protection coordination at 9 months. Disturbance monitoring at 15 months or the in-service date, whichever is later, for new sites, and 36 months for sites already running.

Sites in service within 12 months of the effective date can ask NERC and their Regional Entity for an extension on communications and monitoring equipment, with evidence of circumstances beyond their control [1].

Why NERC says voluntary steps were not enough

NERC’s case rests on incident reviews. In a 2024 Eastern Interconnection event, a 230 kV line fault led to the loss of about 1,500 MW of voltage-sensitive load that operators had not anticipated, and NERC found it was entirely data center-type load [1]. A second review in ERCOT traced repeated load drops to crypto-mining facilities whose power supplies shut down almost instantly on voltage dips [1]. The pattern NERC describes is the same each time: a normally cleared fault, sites switching to backup power to protect equipment, and a sudden need for generation to rebalance [1].

NERC had already issued a May 2026 Level 3 alert with seven “essential actions” [1]. Its March 2026 gap assessment concluded that existing standards “are inadequate to address the risks posed by emerging large loads” [1]. NERC wants FERC to move on an expedited basis, citing that ballot support [1].

Where the sides stand

NERC argues it is regulating only where the physics require it, and that registration rules approved early would let Regional Entities start outreach to new registrants before any standard binds [2].

Data center developers have put an objection on file that goes to the foundation. EdgeConneX, a developer with data centers in 26 U.S. cities, asked FERC on November 20 to reject the registration rules in RR27-1 [5]. Its point is about who holds the information. At a colocation site, the servers belong to tenants, so the building owner “may not possess the information necessary” to supply the modeling data CLO-001-1 asks for, and lease confidentiality terms often bar sharing what it does have [5]. The same gap applies to real-time data and Operating Instructions under CLO-002-1, EdgeConneX says [5].

NERC saw this coming. Responding to stakeholders, it acknowledged that compliance “should fall on those who have the authority or capability to carry them out,” but kept its definitions and pointed to Regional Entities sorting out registration structures case by case [5]. EdgeConneX calls that a “blank check” [5]. It argues the existing tools for shifting compliance, joint registrations and written transfers, depend on tenants agreeing to register, and that tenants “have little incentive” to without a requirement [5]. EdgeConneX says the Data Center Coalition, ERCOT, Google and Microsoft raised the same concern in comments to NERC [5].

Utilities and grid operators have no substantive comments in either docket in the record this column draws on. Their role is spelled out in CLO-001-1 regardless: they write the interconnection requirements and run the studies [1].

What I’m watching

December 17: comments in RD27-3, and whether any developer carries the tenant argument from the registration docket into the standards docket, where the data obligations actually sit [3]. March 1, 2027: NERC’s workplan for the next phase, starting with ride-through performance [1].

FERC has both petitions, and the RR27-1 comment period has closed [4]. The order on registration will have to say whether the owner of a building counts as the operator of a data center whose servers belong to someone else.

Owen Hollis

Key dates

  • Comments due on NERC's computational load standards (RD27-3)
  • NERC informational filing due with its workplan for further computational load standards

Which data centers would have to follow NERC's new computational load standards?

Sites with total connected load of 50 MW or more, supplied through equipment connected at 100 kV or higher from one or more points of connection [1]. NERC says that threshold covers about 86% of the computational load it projects by the end of 2027 [2].

When are comments due on NERC's data center reliability standards at FERC?

5 p.m. Eastern on December 17, 2026, in Docket RD27-3 [3]. NERC has asked FERC for an expedited comment period and expedited action [1].

When would the NERC CLO standards take effect?

On the first day of the first calendar quarter after FERC's approval order takes effect, with requirements phased in over 3 to 36 months after that [1]. Existing sites get 36 months to install disturbance monitoring equipment [1].

Does a data center have to follow grid operator instructions under the NERC proposal?

Yes. Proposed CLO-002-1 requires each Computational Load Operator to comply with Operating Instructions from its Transmission Operator, Balancing Authority or Reliability Coordinator, unless the action cannot be physically carried out or would violate safety, equipment, regulatory or statutory requirements [1,5].

Are colocation tenants covered by NERC's data center registration rules?

The proposal does not say so explicitly. NERC defines the registered entities as whoever owns and maintains, or operates, the site, and leaves case-by-case structures to Regional Entities, which EdgeConneX told FERC is too uncertain to approve [2,5].

This column draws on NERC's two petitions and on the EdgeConneX comments, not on the full exhibits filed with the standards petition (the standards text, implementation plans, technical rationales and development record); where the petition and the standards text differ, the standards text controls. The 3,900 MW figure for the July 2026 event is NERC's preliminary estimate, and its review of that event was not complete when it filed. FERC has not acted on either petition or on NERC's requests for expedited treatment. The positions of the Data Center Coalition, ERCOT, Google and Microsoft are described only as EdgeConneX characterizes their comments to NERC; none of them had filed comments at FERC in either docket in the record this column draws on, and no ratepayer advocate or state commission had either. Neither petition gives a count of sites or entities that would have to register.

  1. 1Petition of the North American Electric Reliability Corporation for Approval of Reliability Standards to Support the Integration of Computational Load and Request for Expedited Action, Docket No. RD27-3-000North American Electric Reliability Corporation · November 16, 2026 · elibrary.ferc.gov
  2. 2Petition for Approval of Revisions to the NERC Rules of Procedure Regarding Computational Load and Request for Expedited Action, Docket No. RR27-1-000North American Electric Reliability Corporation · October 21, 2026 · elibrary.ferc.gov
  3. 3Combined Notice of Filings #1 (including Docket No. RD27-3-000)Federal Energy Regulatory Commission · November 17, 2026 · elibrary.ferc.gov
  4. 4Combined Notice of Filing #1 (including Docket No. RR27-1-000)Federal Energy Regulatory Commission · October 22, 2026 · elibrary.ferc.gov
  5. 5Motion to Intervene and Comments of EdgeConneX, Inc., Docket No. RR27-1-000EdgeConneX, Inc. · November 20, 2026 · elibrary.ferc.gov

Filed under: NERC / reliability standards / data centers / computational load / ride-through / registration