SDG&E's Large-Load Terms at FERC: Security for the Full Life of the Upgrade, Posted Before Construction Starts

In Docket ER27-521, San Diego Gas & Electric asks data center customers to secure the present value of an upgrade's whole revenue requirement, held for ten years after it enters service. DesertLink, a transmission-only owner, asks for a 20-year revenue floor instead.

Owen HollisLoad Factor News

Load Ledger
ItemBodyLoadStageSrc
SDG&E large load interconnection process, pro forma interconnection agreement, lifecycle-value security and FILI serviceFERC Docket ER27-521 (SDG&E)50 MW or greater peak loadfiled Nov. 16, 2026; effective date requested Feb. 16, 2027[1]
DesertLink large load procedures and cost recovery agreement (20-year minimum transmission revenue contribution)FERC Docket ER27-534 (DesertLink)50 MW or greater peak loadfiled Nov. 16, 2026; effective date requested Jan. 16, 2027[3]
Constellation request to move utility comment date to Dec. 16FERC Dockets ER27-508, ER27-513, ER27-521—pending[4]

San Diego Gas & Electric has filed its large-load tariff at FERC, Docket ER27-521, and its answer to the cost question is the bluntest in California: a data center customer posts security equal to the present value of an upgrade’s entire forecast revenue requirement before construction starts [1]. The November 16 filing is SDG&E’s response to FERC’s June 18 show cause order for CAISO and its transmission owners, Docket EL26-71 [1]. It names no project and no megawatts. SDG&E says it has no existing or nearly complete agreements with large loads [1].

This column covered CAISO, PG&E and SCE on November 21 and left SDG&E for later. Here it is, alongside DesertLink, LLC, a transmission-only owner that filed in ER27-534 the same day [3].

The San Diego terms, docket by docket

SDG&E amends its Transmission Owner Tariff rather than writing a new one, and borrows the shape of generator interconnection [1]. The pieces:

  • Definition. A Large Load is “a new customer, located at a single site behind one or more points of interconnection to the CAISO Controlled Grid, and that has a peak load of 50 MW or greater” [1]. SDG&E drops FERC’s suggested above-69 kV test because some of its CAISO-controlled lines operate at 69 kV, and it keeps co-located load in, saying an exclusion “could limit the ratepayer protections” [1].
  • Entry costs. A $50,000 non-refundable application fee, a $100,000 System Impact Study deposit, $100,000 more for a Facilities Study and $200,000 more if an electromagnetic transient (EMT) study is required [1].
  • Queue. Serial and first-come, with applications accepted on a rolling basis; each study carries a 60-day default estimate [1]. A customer gets 30 days to sign a tendered interconnection agreement or ask SDG&E to file it unsigned, or the request is withdrawn [1].
  • Data. Hourly load profile, ramping, ride-through, curtailment ability, behind-the-meter generation, and disclosure of any similar requests for the same load [1].
  • Interim service. Flexible Interim Load Interconnection (FILI), meaning partial energization before upgrades are done, with limits set in the study rather than in real time [1].

SDG&E asks for a February 16, 2027 effective date [1]. FERC’s notice sets comments for December 7 [2].

Who pays, and for how long

The customer pays in cash for interconnection facilities and advance-funds direct assignment facilities [1]. For network upgrades, the security matches the present value of their “forecast lifecycle revenue requirement,” capital and O&M, at SDG&E’s authorized cost of capital [1]. That security runs from the customer’s go-ahead to build until ten years after the upgrades enter service [1].

The mechanics, in order:

  1. The customer picks a minimum annual revenue schedule, inflation-escalated or levelized, whose present value equals the lifecycle requirement [1].
  2. Each year SDG&E counts “Deemed Transmission Revenues”: the applicable access charge rate times the load’s metered withdrawals [1].
  3. A shortfall against the minimum is drawn from the security [1].
  4. If the load will never reach operation, or shuts down, SDG&E draws whatever remains, “effectively, an ‘exit fee’” [1].
  5. Every draw is booked as a credit in the Transmission Revenue Balancing Account Adjustment, lowering rates for other customers [1].

SDG&E says that for upgrades at 200 kV and above this is designed to eliminate cost shifts to ratepayers in its own and other access charge areas; below 200 kV, within its own area [1]. It also concedes a cost of its design. Because the amount is fixed from forecasts, the customer may post “more security than turns out to be necessary,” a risk SDG&E judges worth the “commercial certainty and administrative simplicity” [1].

Where SDG&E itself serves the data center at retail, it will not post security to itself; it commits to impose comparable requirements through retail agreements to the extent California law allows [1].

SDG&E says its approach is “substantively aligned” with SCE’s and DesertLink’s [1]. It does not list PG&E in that sentence.

DesertLink, owner of the Harry Allen to Eldorado 500 kV line and a non-load-serving owner, gets to a similar result by a different route [3]. Its cost recovery agreement sets a 20-year Minimum Transmission Revenue Contribution per upgrade; the customer pays any gap between that floor and the transmission revenue its load produces [3]. Operational security equals 100% of the remaining commitment, reduced dollar for dollar by security already posted under a retail agreement, and leaving triggers a lump-sum termination fee [3]. Its study deposit is $250,000, with readiness deposits that bring the total to 20% of estimated upgrade cost [3]. DesertLink calls its 100% figure “conservative” and says it will look at lower requirements with CAISO and stakeholders [3].

Where the sides stand

Ratepayer advocates saw this coming from the other direction. In October, the Public Advocates Office at the CPUC told CAISO it “should not assume that the PTOs will sufficiently address these deficiencies” [5]. Its example was SDG&E, which had argued in September that CAISO should not say every utility would add flexible interconnection provisions, because FERC had not found the utility tariffs deficient on that point [5]. SDG&E’s November filing does add FILI [1]. Whether a utility-by-utility answer satisfies the Public Advocates Office is for its FERC comments to say.

State regulators’ staff wanted upgrade costs on the loads. CPUC staff wrote that they “consider concurrence projects inherently load-driven reliability costs appropriately borne in full by the precipitating load(s)” [6]. Concurrence is CAISO’s sign-off on a utility’s upgrade outside annual planning, and SDG&E’s pro forma agreement requires it [1].

Data center developers accept the principle and question the stacking. Microsoft said large-load customers should pay for upgrades “reasonably attributable to their interconnection requests,” and asked for “safeguards against duplicative cost recovery or financial security requirements” [7]. DesertLink’s credit for retail security addresses that directly [3]. SDG&E’s letter answers it only for retail customers it serves itself [1].

Generators want time. Constellation asked FERC to push the December 7 comment date on SDG&E, PG&E and SCE to December 16, citing linked dockets and the Thanksgiving holiday [4].

What I’m watching

  • December 7: comments on SDG&E and DesertLink, unless FERC grants Constellation’s motion [2,4].
  • January 16 and February 16, 2027: the effective dates DesertLink and SDG&E request [1,3].

The open question is the one SDG&E raised against itself: whether full lifecycle security, sized on forecasts and posted before a shovel moves, is protection or a barrier for a load that may take years to ramp.

Owen Hollis

Key dates

  • Comments due on SDG&E (ER27-521) and DesertLink (ER27-534) filings
  • Effective date DesertLink requests
  • Effective date SDG&E requests

How much security does SDG&E require from a data center for transmission upgrades?

An amount equal to the present value of the upgrades' forecast lifecycle revenue requirement, capital and O&M, at SDG&E's FERC-authorized cost of capital [1]. It must be posted before construction of the upgrades begins and is held until ten years after they enter service [1].

Does SDG&E's FERC filing let a data center connect before upgrades are finished?

Yes. SDG&E proposes Flexible Interim Load Interconnection service, with withdrawal limits set in the interconnection study and curtailment terms in a further agreement with CAISO where real-time curtailment is needed [1].

What happens to the security if a data center never comes online in San Diego Gas & Electric territory?

The customer must notify SDG&E, which draws all remaining security, in effect an exit fee [1]. Draws are credited through SDG&E's Transmission Revenue Balancing Account Adjustment and lower access charge rates for other customers [1].

When are comments due on SDG&E's large load filing at FERC?

5 p.m. Eastern on December 7, 2026, per FERC's notice [2]. Constellation has asked FERC to move it to December 16 to match the CAISO filing [4].

What does SDG&E charge to apply for a large-load interconnection study?

A $50,000 non-refundable application fee, a $100,000 System Impact Study deposit, $100,000 more for a Facilities Study and $200,000 more if an EMT study is needed [1].

This column draws on the SDG&E and DesertLink transmittal letters, not on the full redlined tariffs, pro forma agreements or DesertLink's testimony and spreadsheets; where a letter and the tariff text differ, the tariff controls. The Public Advocates Office, CPUC staff and Microsoft positions come from comments on CAISO's September 24 draft proposal, filed before SDG&E's tariff existed; none of the three had filed comments at FERC on ER27-521 in the record this column draws on. FERC had not acted on Constellation's request to move the December 7 comment date as of publication. Neither filing names a data center project or states a megawatt total of pending large-load requests, and SDG&E reports no existing or nearly complete agreements with such customers. The other transmission-only owners' filings in the same proceeding are not covered here.

  1. 1Transmission Owner Tariff Revisions of San Diego Gas & Electric Company (transmittal letter), Docket No. ER27-521-000San Diego Gas & Electric Company · November 16, 2026 · elibrary.ferc.gov
  2. 2Combined Notice of Filings #1 (including Docket Nos. ER27-521-000 and ER27-534-000)Federal Energy Regulatory Commission · November 18, 2026 · elibrary.ferc.gov
  3. 3Proposed Revisions to the DesertLink, LLC Transmission Owner Tariff to Provide for Large Load Interconnection and Cost Recovery (transmittal letter), Docket No. ER27-534-000DesertLink, LLC · November 16, 2026 · elibrary.ferc.gov
  4. 4Expedited Motion for a Nine-Day Extension of Comment Deadline, Docket Nos. ER27-513-000, ER27-508-000 and ER27-521-000Constellation Energy Generation, LLC · November 19, 2026 · elibrary.ferc.gov
  5. 5Comments on Large Loads Draft Final Proposal and 10/1 MeetingPublic Advocates Office at the California Public Utilities Commission · October 15, 2026 · stakeholdercenter.caiso.com
  6. 6Comments on Large Loads Draft Final Proposal and 10/1 MeetingCalifornia Public Utilities Commission · October 16, 2026 · stakeholdercenter.caiso.com
  7. 7Comments on Large Loads Draft Final Proposal and 10/1 MeetingMicrosoft · October 15, 2026 · stakeholdercenter.caiso.com

Filed under: California / SDG&E / large load interconnection / cost allocation / data centers / financial security