SPP's Answer to FERC on Large Loads: Regional Rates Cover the First $25 Million of a Delivery Point, the Customer Pays the Rest
In FERC Docket ER27-577, the Southwest Power Pool caps the upgrade cost other customers carry for any new load connection, a rule its state regulators pushed through after the members' committee passed nothing. A companion filing, ER27-578, offers non-firm service for loads that stop buying above $25/MWh.
| Item | Body | Load | Stage | Src |
|---|---|---|---|---|
| Load Safe Harbor Limit: regional funding capped at lesser of $500,000/MW or $25 million per delivery point request; excess directly assigned up to 40 years | FERC Docket ER27-577 (SPP) | $25 million cap equals 50 MW at $500,000/MW | filed Nov. 19, 2026; effective date requested Feb. 17, 2027 | [1] |
| Price Adaptive Load Service: non-firm, usage-billed, $25/MWh bid cap, one- to ten-year terms | FERC Docket ER27-578 (SPP) | — | filed Nov. 19, 2026; order requested by Feb. 17, 2027; launch targeted Q2 2028 | [2] |
| High Impact Large Load service agreements, mandatory review of alternative transmission technologies, searchable upgrade cost data, co-located generation rules | FERC Docket ER27-559 (SPP) | HILL: 10 MW or more at 69 kV or below; 50 MW or more above 69 kV | filed Nov. 18, 2026; effective date requested Feb. 16, 2027 | [3] |
| Large load show cause proceeding (co-located load rates and remaining directives) | FERC Docket EL26-68 | — | SPP response due Nov. 20, 2026 | [1] |
When SPP’s Markets and Operations Policy Committee took up the cost rule for new load connections on October 13, it “failed to pass any motion” on it [1]. The Regional Tariff Working Group had not approved it in an October 12 vote [1]. On November 19 the Southwest Power Pool filed it at FERC anyway, as FERC Docket ER27-577, because its state regulators approved it 14 to 1, with one abstention, and SPP’s bylaws give them primary say over cost allocation [1]. The rule decides how much of the upgrade bill for a new data center connection lands on everyone else in SPP’s regional rates.
ER27-577 is one of three filings SPP made this week in answer to FERC’s June 18 large-load show cause order, Docket EL26-68 [1]. The others are ER27-578, a new non-firm service, and ER27-559, a set of contract and transparency changes [2,3]. In July, SPP told FERC that much of its forecasting uncertainty comes from “unprecedented load interconnection requests associated with data centers and other large commercial and industrial customers” [6].
What the safe harbor caps
Today, SPP’s tariff has no limit on the network upgrade cost that can be spread across regional rates for a delivery point request, in dollars per megawatt or in total, “regardless of the costs relative to the load requested or whether the load materializes” [1]. SPP calls that “precisely the gap the Show Cause Order identified” [1].
The fix borrows from 2005. SPP already caps rate-funded upgrades for designating a generator at $180,000 per MW [1]. The new Load Safe Harbor Limit does the same on the load end:
- Regional Base Plan funding covers upgrade cost up to the lesser of $500,000 per MW of requested load or $25 million per request [1].
- Anything above that is directly assigned to the transmission customer that asked for the delivery point, billed as the building utility’s revenue requirement for up to 40 years [1]. After that, the remainder rolls back into regional rates [1].
- The customer posts security sized to the directly assigned amount, declining as the assets depreciate [1].
The $25 million is the 50 MW threshold for a High Impact Large Load (above 69 kV) times $500,000 [1]. So for any request larger than 50 MW, the dollar cap binds. SPP’s own example of why it needed a total: without one, “a 1,000 MW request could qualify for $500 million of Base Plan funding” [1].
The per-MW figure comes from SPP’s history. Delivery point studies from 2012 to 2026 that needed upgrades ran about $177,000 per MW at the median, $378,000 at the 75th percentile and $1.018 million at the 95th [1]. SPP’s existing transmission plant works out to about $422,000 per MW net of depreciation and $572,000 gross [1]. Most delivery point requests need no upgrade at all, SPP adds [1].
What it does to cost and timing
For a data center developer, the cap turns an open question into a fixed bill. SPP describes the directly assigned share as “a fixed payment that does not depend on whether, when, or at what level the load is energized” [1]. Payments start when the utility sets a revenue requirement for the upgrade [1]. The rule applies only to requests submitted on or after the effective date, which SPP asks to be February 17, 2027 [1].
Readers of the MISO column on November 17 will see a different design. MISO’s agreements bill the load for upgrades whether or not it shows up; SPP keeps a regional share of the first $25 million and assigns only the excess [1].
For loads that can switch off, ER27-578 creates Price Adaptive Load Service. The load bids into SPP’s day-ahead and real-time markets, and its bids are capped at $25/MWh [2]. It pays hourly non-firm point-to-point rates on what it uses, capped monthly, for terms of one to ten years [2]. No upgrades are built for it and no capacity obligation attaches [2]. SPP’s simulations of ten 200 MW loads found that raising the cap from $20 to $25 lifted the loads’ real-time load factor from 45% to 60%, while average real-time prices rose $0.20/MWh; going from $25 to $30 raised prices another $0.80/MWh [2]. SPP targets launch in the second quarter of 2028 [2].
ER27-559 makes every High Impact Large Load study evaluate grid-enhancing technologies and explain, technology by technology, why any are rejected [3]. It also writes the existing operating rules for these loads (telemetry, remote disconnect, ride-through) into service agreements, and requires utilities to report large-load upgrades and costs in a searchable SPP planning file [3].
Where the sides stand
State regulators split before they agreed. At the Cost Allocation Working Group on October 1, members debated “whether existing customers should fund a portion of upgrades associated with new load” and whether 40 years matches large-load contracts “closer to 20 years” [5]. The group backed a different version, a flat $21.25 million cap for loads of 50 MW or more, 6 to 4 with five abstentions; Arkansas, Missouri, North Dakota and South Dakota voted no [5]. SPP staff warned that a megawatt bright line “would incentivize load projections” that are “unrealistically low” and give no protection below 50 MW [5]. The CARE Team then approved the per-MW version with direct assignment limited to 20 years, and the Regional State Committee’s November 16 motion set the limit at no more than 40 [1].
Missouri had told FERC in August that issues of “transparency and the avoidance of cost shifting” are particularly important to state regulators “who bear the responsibility of setting retail rates that include FERC-jurisdictional transmission costs” [7].
Utilities raised their own list. Evergy and AEP presented joint comments to the working group questioning the $25 million cap, its reach to all loads, the 40-year term, prospective-only application, annual review and how revenue requirements would be calculated [5].
Large buyers have said less on the record. The Corporate Energy Buyers Association backed the abeyance in August so proposals could be built for “commercial viability and legal durability” [8]. It had not filed on these dockets in the record this column draws on.
On PALS rates, the working group voted 6 to 2, with seven abstentions, to recommend charging only off-peak transmission rates, since the service would at times be curtailed ahead of other non-firm customers and is capped at $25 [5]. SPP staff answered that a departure from the existing rate design would need “clear justification” [5]. The filed tariff charges the on-peak or off-peak rate for each hour of use [2].
What I’m watching
- December 9 and 10: comments on ER27-559 and ER27-577 [4]. Watch whether Evergy, AEP or the states that voted no in October take the 20-year term or the $25 million cap to FERC [5].
- SPP’s EL26-68 response, due November 20, which SPP says covers rates for co-located load [1].
The filing answers the working group’s term question with a number, 40 years, and leaves the other half open: whether a data center customer will sign up for a payment stream that long [1,5].
Owen Hollis
Key dates
- Comments due on SPP's high impact large load filing (ER27-559)
- Comments due on SPP's Load Safe Harbor Limit (ER27-577)
- Effective date SPP requests for ER27-559
- Effective date SPP requests for the safe harbor; date by which it asks FERC to rule on PALS
Reader questions
What is SPP's Load Safe Harbor Limit?
It is a cap on how much network upgrade cost for a new or changed load delivery point gets spread across SPP's regional rates: the lesser of $500,000 per MW requested or $25 million [1]. Cost above the cap is directly assigned to the transmission customer that asked for the delivery point [1].
How long does a data center customer in SPP pay for upgrades above the safe harbor?
Up to 40 years, as a revenue requirement the transmission owner calculates under its normal method; after that, any remaining cost goes back into regional Base Plan funding [1]. The customer must post financial security that declines as the upgrades depreciate [1].
Does SPP's new cost cap apply to projects already in the study queue?
No. SPP says it applies only to delivery point requests submitted on or after the effective date FERC accepts, which SPP asked to be February 17, 2027 [1]. Ongoing and past delivery point studies are not affected [1].
When are comments due on SPP's large load filings at FERC?
FERC's notice sets 5 p.m. Eastern on December 9, 2026 for the high impact large load filing, ER27-559, and December 10, 2026 for the cost cap filing, ER27-577 [4]. No comment date had been noticed for the Price Adaptive Load Service filing, ER27-578 [4].
What is Price Adaptive Load Service in SPP?
It is a proposed non-firm transmission service for loads that bid into SPP's markets and stop drawing power when prices pass $25/MWh, with terms of one to ten years and no new upgrades built for it [2]. SPP targets launching it in the second quarter of 2028 [2].
A note on sourcing
This column draws on SPP's transmittal letters, not on the redlined tariff sheets, business practices or the two affidavits filed with the cost cap; where a letter and the tariff text differ, the tariff controls. The per-MW cost percentiles and transmission plant values are SPP's figures from its own study history and utility rate data. The positions of state regulators and of Evergy and AEP come from the Cost Allocation Working Group minutes and SPP's description of committee votes; those utilities had not filed comments at FERC on these dockets in the record this column draws on, and no data center developer had either. The Corporate Energy Buyers Association and the Missouri PSC positions quoted here were filed in August, before the proposals were final. FERC had not noticed a comment date for the Price Adaptive Load Service filing, ER27-578. SPP's separate response in Docket EL26-68, which it says covers transmission and ancillary service rates for co-located load, was due November 20 and is not part of this column. None of the filings names a data center project or states a megawatt total of pending large-load requests.
Sources
- 1Submission of Tariff Revisions to Establish Load Safe Harbor Limit for Delivery Point Costs (transmittal letter), Docket No. ER27-577-000Southwest Power Pool, Inc. · November 19, 2026 · elibrary.ferc.gov
- 2Submission of Tariff Revisions to Add the Price Adaptive Load Service (transmittal letter), Docket No. ER27-578-000Southwest Power Pool, Inc. · November 19, 2026 · elibrary.ferc.gov
- 3Submission of Tariff Revisions for High Impact Large Loads and Non-Transmission Facilities in Response to Show Cause Order (transmittal letter), Docket No. ER27-559-000Southwest Power Pool, Inc. · November 18, 2026 · elibrary.ferc.gov
- 4Combined Notice of Filings #1 (including Docket Nos. ER27-559-000 and ER27-577-000)Federal Energy Regulatory Commission · November 19, 2026 · elibrary.ferc.gov
- 5Cost Allocation Working Group Meeting Minutes, October 1, 2026Southwest Power Pool, Inc. · October 1, 2026 · spp.org
- 6Informational Report of Southwest Power Pool, Inc., Docket No. EL26-68-000Southwest Power Pool, Inc. · July 20, 2026 · elibrary.ferc.gov
- 7Comments of the Public Service Commission of the State of Missouri in Support of the Joint Movants' Request for Abeyance, Docket No. EL26-68-000Missouri Public Service Commission · August 7, 2026 · elibrary.ferc.gov
- 8Answer of Corporate Energy Buyers Association in Support of the Motion for Abeyance, Docket No. EL26-68-000Corporate Energy Buyers Association · August 7, 2026 · elibrary.ferc.gov
Filed under: large load interconnection / cost allocation / transmission / data centers / non-firm service / state regulators