MISO Files Its Promised Cost Recovery Agreements: Data Center Hosts Owe 20 Years of Revenue on Upgrades, Whether or Not the Load Shows Up
In FERC Docket ER27-526, MISO and its transmission owners propose a $250,000 application, security equal to upgrade capital cost and a yearly true-up for the utilities that serve large loads. A companion filing, ER27-527, offers permanent non-firm service cut off above $100/MWh, but not before 2029.
| Item | Body | Load | Stage | Src |
|---|---|---|---|---|
| Large Load Project Review, LL-CRA and LLITO-CRA cost recovery agreements, Interim NITS, Firm Service Step Up | FERC Docket ER27-526 (MISO and MISO Transmission Owners) | applies to loads of 50 MW or more | filed Nov. 16, 2026; effective date requested Feb. 14, 2027 | [1] |
| Grid Responsive Integration Transmission Service (GRITS) | FERC Docket ER27-527 (MISO) | — | filed Nov. 16, 2026; implementation no earlier than Jan. 1, 2029 | [3] |
| Large Load Addition Resource Study (LARS), paired load and generation | FERC Docket ER27-25 (MISO) | 200 MW or more | pending; MISO answered protests Nov. 9, 2026 | [9] |
| Show cause proceeding on MISO large and co-located loads | FERC Docket EL26-70 | — | in abeyance; answers due Dec. 16, 2026 | [4] |
“Put plainly,” MISO told FERC on Monday, the customer serving a large load “is always responsible for the costs of the Large Load Network Upgrade(s)” [1]. That sentence is the answer MISO and its transmission owners owed the region by November 16, the deadline FERC set when it paused its show cause case in August [4]. It arrives in FERC Docket ER27-526, with a companion service filing in ER27-527 [1,3]. What it buys is easiest to see in dollars: the 56 load requests approved in MISO’s 2026 transmission plan averaged $145 million in network upgrades each, and those above 200 MW averaged $201 million, by MISO’s own count [9].
The filing, piece by piece
FERC’s June 18 order found MISO’s tariff short on large-load study rules, cost-shift protection and flexible service, and invited regional fixes [1,4]. MISO answered in installments: a zero-injection generator agreement, reliability rules that define a Large Load as 50 MW or more at one substation, and the LARS paired-generation study this column covered on October 23 [1]. ER27-526 is the omnibus that ties them together [1].
- Large Load Project Review. Every request for transmission service to a Large Load goes through one study, run three times a year and meant to take about five months [1]. Only the transmission customer, usually the load-serving utility, may apply [1]. The price of entry is a $250,000 nonrefundable fee and a $100,000 study deposit, plus another $100,000 if MISO runs the electromagnetic transient study [1]. The megawatt figure and service type cannot change after filing [1]. The first deadline is March 1, 2027 [1].
- Two cost recovery agreements. The LL-CRA covers upgrades inside the pricing zone where the load connects; the LLITO-CRA covers upgrades in a neighboring owner’s zone [1]. MISO will not approve the upgrades in its transmission plan until the agreements are signed or filed unexecuted, and no service starts under an unexecuted one until FERC accepts it [1].
- A dashboard. Transmission owners must report proposed large-load additions by zone, the upgrades each load needs and their estimated costs, for public posting on a searchable map [1].
- Interim service. Interim NITS lets a load draw a non-firm amount while its upgrades are built [1]. It is curtailed after non-firm point-to-point service but ahead of firm service, and it stays in the capacity forecast, so it is no capacity exemption [1].
What the agreements do to cost
Each transmission owner chooses whether to roll the upgrade into its zonal rate or assign it directly to the customer, and records the election in the agreement [1]. Rolled in, the customer owes a Total Required Revenue Commitment: return on and of the investment over 20 years, plus depreciation, operations and taxes [1]. Each year the owner and MISO compare that commitment with the transmission revenue the load actually produced. If revenue falls short, the customer pays the gap as a Supplemental Payment, and the owner credits it against its revenue requirement [1].
The transmission owners’ witness worked one illustrative case [2]:
| Item | Figure |
|---|---|
| Requested load | 500 MW |
| Upgrades (three, in service Dec. 2027-2029) | $100,000,000 |
| 20-year fixed charge rate | 13.7024% |
| Total Required Revenue Commitment | $274,048,000 |
| Yearly commitment once all are in service | $13,702,400 |
The yearly figure steps up as each upgrade energizes [2]. MISO’s own shorthand: a $10 million yearly commitment against $7 million of revenue means a $3 million check [1]. Security equals the upgrades’ capital cost, due within 45 days of signing, as a letter of credit, surety bond or parent guaranty; the customer may ask to reduce it, down to a floor tied to what is still owed [1]. The agreement ends 20 years after the last upgrade enters service, or sooner once the commitment is satisfied [1]. With no other changes, MISO says, “the zonal rate charged to other customers will not increase” [1].
Note the structure. Ordinary network charges count toward the minimum, and only the shortfall is billed. That is the crediting the Citizens Utility Board of Wisconsin objected to in ATC’s Microsoft agreements, covered here yesterday. MISO sets its floor at the upgrades’ own 20-year revenue requirement [1,2].
Two limits. Projects already in Expedited Project Review stay there and neither must nor may move to the new process [1]. And nothing binds the data center: MISO calls the transmission customer “merely a pass through” in many cases and leaves states to push costs further down [1].
GRITS and the $100 line
ER27-527 is the permanent flexible option FERC asked for [3]. A load sets a total limit and a firm slice anywhere from zero to all of it; MISO’s example is a 500 MW data center taking 200 MW firm and 300 MW non-firm [3]. The non-firm part is interrupted whenever its price exceeds $100/MWh, a cap MISO says historically would have allowed service in more than 95% of hours [3]. A capacity advisory in the same balancing area cuts all of it [3]. In return that portion may be excluded from the obligation to buy capacity [3]. Co-located generation must register as a resource, and regulation and black start are billed on gross load, so nobody nets away those charges [3].
ISO New England put its re-dispatch line at $250 in its November 13 filing. MISO’s is lower and its date is later. Software changes push the earliest start to January 1, 2029, and the rates are not written; MISO and its owners intend to file them, or a status report, before March 16, 2027 [3].
Where the sides stand
The October filings on LARS set the test this package now faces.
The Organization of MISO States said it “cannot support LARS in its current form” and wanted a cost framework settled before implementation, one reaching later reliability projects, congestion and ancillary services, not only directly attributable upgrades [5]. An upgrade, it wrote, should not lose its cost attribution by becoming part of a regional project [5].
Consumer advocates from Iowa, Michigan, Illinois, Wisconsin, Minnesota and Indiana protested that “the cost-causer, not other ratepayers, should be responsible for all network upgrades resulting from the Large Load” [6]. In a November 12 answer, six of them added: “Financial assurance and cost causation perform different functions” [7]. Security, they argued, cannot help if a load-driven project is classified for broad recovery first [7].
The Data Center Coalition backed LARS and asked for a cost framework that would “reflect cost causation, recognize benefits to the broader transmission system, and avoid inappropriate cost shifts to existing customers” [8].
MISO answered that LARS “does not create any new cost shift opportunities” and promised the agreements for November 16 [9]. ER27-526 makes them apply to LARS cycles starting on or after February 14, 2027, if FERC accepts both filings [1].
American Municipal Power, opposing the August pause, warned the upgrade costs were “likely to be in the billions of dollars” and that MISO and its owners could not design the fix alone [4]. MISO’s letter concedes full alignment “was not achieved on every aspect” [1].
What I’m watching
- December 16, 2026: answers to show cause responses in EL26-70 [4]. Watch whether OMS and the advocates say the agreements reach the later reliability projects they named [5,7].
- March 1, 2027: the first application deadline, if FERC acts on a February 14 effective date [1].
The agreements cover the upgrades listed from the study [1]. Whether a project relabeled in a later planning cycle still carries the data center’s name is the question OMS asked, and this filing does not answer it in so many words [5].
Owen Hollis
Key dates
- Answers due to responses in MISO show cause proceeding (EL26-70)
- Effective date MISO requests for ER27-526
- First Large Load Project Review application deadline
- Earliest GRITS implementation date, per MISO
Reader questions
What does MISO's large load cost recovery agreement require?
The utility or other transmission customer serving a large load signs an agreement covering the upgrades MISO's study identifies, posts security equal to their capital cost within 45 days, and owes a yearly minimum for up to 20 years after the last upgrade enters service [1]. If its transmission charges for the load fall short of that minimum, it makes a supplemental payment credited against the transmission owner's revenue requirement [1,2].
Does the data center itself sign MISO's cost recovery agreement?
No. The parties are MISO, the transmission owner and the transmission customer taking service on the load's behalf, usually the load-serving utility [1]. MISO says states remain free to pass costs to the data center or require agreements with it [1].
When could data centers apply under MISO's new Large Load Project Review?
MISO asked FERC for a February 14, 2027 effective date and set the first application deadline for March 1, 2027 [1]. Each cycle is designed to take about five months, with three cycles a year [1].
What is MISO's GRITS service for data centers?
Grid Responsive Integration Transmission Service lets a large load take part of its demand as permanent non-firm service that is interrupted when its price exceeds $100/MWh or when a capacity advisory is declared [3]. MISO says the earliest it can start is January 1, 2029, and rates are still to be filed [3].
A note on sourcing
This column draws on MISO's two transmittal letters and the transmission owners' cost testimony; it does not draw on the full pro forma agreements or the redlined tariff sheets, and MISO says the tariff sheets control where its letter differs. The $100 million, $274 million and $13.7 million figures are the transmission owners' illustrative example for a generic utility, not any real project. The $145 million and $201 million averages are MISO's figures for load requests approved in MTEP26, from its LARS answer. The positions attributed to the Organization of MISO States, consumer advocates and the Data Center Coalition were filed on MISO's LARS proposal (ER27-25) before the November 16 filings; none of them had commented on ER27-526 or ER27-527 in the record this column draws on. FERC had not noticed a comment date for either filing as of November 16; MISO asked for a 30-day comment period. GRITS rates have not been filed. No megawatt figure for any specific data center appears in either filing.
Sources
- 1Large Load Review, Cost Recovery and Transmission Services Filing (transmittal letter), Docket No. ER27-526-000Midcontinent Independent System Operator, Inc. · November 16, 2026 · elibrary.ferc.gov
- 2Testimony and Exhibits of Greg M. Gudeman on the pro forma cost recovery agreements, Docket No. ER27-526-000 (Tab E)MISO Transmission Owners · November 16, 2026 · elibrary.ferc.gov
- 3Grid Responsive Integration Transmission Service for Large Loads (transmittal letter), Docket No. ER27-527-000Midcontinent Independent System Operator, Inc. · November 16, 2026 · elibrary.ferc.gov
- 4Letter order granting abeyance, Docket No. EL26-70-000, 196 FERC ¶ 61,133Federal Energy Regulatory Commission · August 14, 2026 · elibrary.ferc.gov
- 5Notice of Intervention and Comments of the Organization of MISO States, Docket No. ER27-25-000Organization of MISO States · October 23, 2026 · elibrary.ferc.gov
- 6Joint Protest of the Iowa Office of the Consumer Advocate et al., Docket No. ER27-25-000Iowa Office of the Consumer Advocate · October 23, 2026 · elibrary.ferc.gov
- 7Motion for Leave to Answer and Answer of MISO Consumer Advocates, Docket No. ER27-25-000Citizens Utility Board of Michigan · November 12, 2026 · elibrary.ferc.gov
- 8Motion to Intervene and Comments of Data Center Coalition, Docket No. ER27-25-000Data Center Coalition · October 23, 2026 · elibrary.ferc.gov
- 9Motion for Leave to Answer and Answer of MISO to comments and protests, Docket No. ER27-25-000Midcontinent Independent System Operator, Inc. · November 9, 2026 · elibrary.ferc.gov
Filed under: large load interconnection / cost allocation / transmission / data centers / non-firm service