Load Factor Newsby Owen Hollis

Data centers, power demand and the policy fights over both.

Level of government:Federal

ISO New England Files Large-Load Rules Before the Large Loads Arrive: 50 MW, Bring Your Own Capacity, Non-Firm Above $250

In FERC Docket ER27-484, the New England grid operator and its transmission owners answer June's show cause order with a 50 MW definition, three new transmission services starting June 1, 2028, and a cost agreement that makes the data center itself a party.

Owen HollisLoad Factor News

Load Ledger
ItemBodyLoadStageSrc
Large-load tariff revisions, Docket ER27-484-000FERC (ISO New England and transmission owners)Large Load defined at 50 MW or more, above 60 kVfiled Nov. 13, 2026; effective date of Nov. 14 requested[1]
Firm, Interim and Non-Firm Contract Demand ServiceISO New England OATT, new Part II.J—proposed; service from June 1, 2028[1]
Large Load Re-Dispatch Price for non-firm serviceISO New England energy market—proposed at $250/MWh[1]
Large Load Cost Recovery Agreement (new Attachment V)Participating Transmission Owners—proposed; NEPOOL does not join this part of the filing[1]
Bring-your-own-new-capacity rules and capacity market exclusion detailsISO New England—notice language filed; detailed rules planned for 2027[1]

New England’s load has been flat or falling for a decade, and the region is generally long on supply, ISO New England told FERC in its filing on November 13 [1]. In February, its chief executive told six New England senators that no new large data centers had committed to construction [4]. On Friday the grid operator filed rules for them anyway: a 50 MW definition, a requirement to bring new capacity, and a $250 price at which non-firm data centers give way, in Docket ER27-484-000 [1].

The filing answers FERC’s June 18 show cause order, one of six issued that day to every regional grid operator [1]. As this column noted on October 23, MISO’s answer to its own order was the LARS paired-generation process. New England chose a different path. Its proposal is a full set of new transmission services, and it asks FERC to end the show cause proceeding outright if it accepts them [1].

What New England filed

ISO New England filed with the NEPOOL Participants Committee, the transmission owners’ administrative committee and 13 named transmission owners, including Eversource, National Grid, Central Maine Power and Versant Power [1]. FERC had put the case in abeyance for 90 days on August 14 so the region could write its own rules [1].

The operative pieces:

  • A definition. A Large Load is a commercial or industrial customer at one site with gross peak demand of 50 MW or more, connected above 60 kV [1]. The ISO says loads between 20 and 50 MW do not raise the same reliability concerns [1].
  • A door for what exists. A load in operation or “sufficiently under construction” on June 18, 2026, keeps its existing demand outside the rules, measured as the higher of its 10-year hourly peak or the MW figure in its existing agreement [1]. It becomes a Large Load only if it grows 50 MW beyond that [1].
  • An application. A $50,000 nonrefundable fee, a $150,000 study deposit and an affidavit that no duplicate application exists [1].
  • No netting. Behind-the-meter generation gets a netting threshold of zero MW, so a co-located data center cannot offset its load with on-site supply for wholesale settlement [1].
  • Price lists. The ISO would post a searchable list of every network upgrade identified for each Large Load, with cost estimates [1].

Three services and the $250 line

Here is where timing and location get decided. Firm Contract Demand Service requires every identified network upgrade to be in service, and the customer must designate new capacity resources equal to the firm amount it asks for [1]. Interim Contract Demand Service is the waiting room: non-firm, available for up to seven years or as long as the upgrades take, whichever is longer [1]. Non-Firm Contract Demand Service has no capacity requirement at all [1].

Non-firm in New England means something specific. A Large Load on interim or non-firm service is re-dispatched, in whole or part, when its locational marginal price exceeds $250/MWh [1]. The ISO says load zone prices crossed that line in about 1% of hours from 2021 through 2025, and that the figure matches the penalty factor for Replacement Reserves, a service the region already forgoes at that price [1]. A Demand Bid is optional; without one, the ISO schedules the load from its forecast [1].

The capacity piece is a notice, not yet a rule. Loads on interim or non-firm service would be excluded from the Installed Capacity Requirement [1]. What counts as “new” capacity, how it is accredited and where it must sit are left for a filing in 2027 [1]. So a developer reading ER27-484 today learns that it will have to bring capacity, but not what qualifies.

Generators get a narrow definition of “electrically proximate.” On New England’s networked system, the ISO says, a generator one or more substations away would likely not deliver power as if it sat at the same point as the load [1]. The test is whether the generator’s output reaches the load as if the two shared a point or were connected radially [1]. Such a generator enters with zero MW of Network Resource Interconnection Service and can shorten the load’s re-dispatch, but cannot count toward the capacity a firm customer must bring unless it goes through the regular cluster study [1].

The calendar is long. Applications and studies would open June 1, 2027, and service would begin June 1, 2028, the date the ISO says its software will be tested [1]. A project that signs a system impact study agreement with its transmission owner before June 1, 2027, skips the new study process but takes on everything else [1].

Who pays if the data center never shows up

The transmission owners’ answer is to put the data center on the contract. Their proposed Large Load Cost Recovery Agreement is a three-party document among the transmission owner, the customer that takes transmission service and the “Large Load Entity” that owns the load [1].

Their reasoning is about utilities, not data centers. In states without retail choice the distribution utility must take service on the load’s behalf, and if the load “failed to materialize,” that utility would be on the hook for network upgrades that “could easily run to the hundreds of millions of dollars,” the filing says [1]. A side indemnity from the data center might not be enforceable given the utility’s state obligation to serve, so the owners want the load bound directly [1].

The money runs through four channels [1]:

  1. Sole-use facilities paid for directly, including later upkeep.
  2. A monthly Cost Recovery Charge equal to the upgrades’ revenue requirement minus the transmission charges the customer already pays, credited back to other customers.
  3. An exit fee equal to the upgrades’ net book value plus decommissioning.
  4. Credit support, in a form each transmission owner sets in its own appendix.

All non-interconnection upgrades found in a Large Load study are the customer’s sole responsibility, even if a co-located generator joins the study [1].

This is the one piece the region did not fully sign. NEPOOL supported the package but does not join the filing on the agreement and takes no position on the owners’ jurisdiction arguments [1]. The owners concede that a contract with a retail customer “warrants careful jurisdictional analysis,” note that no stakeholder or state entity objected on those grounds, and consent in advance to FERC modifying or severing the cost provisions [1].

Where the sides stand

The region’s market participants voted for the package. Three NEPOOL committees recommended support on November 3, and the Participants Committee supported it on November 12 [1].

The Electric Power Supply Association, which represents competitive generators, has so far weighed in only on timing. It backed the ISO’s request for comments by December 7, citing the filing’s breadth, the holiday and other large-load filings expected November 16 [3]. FERC’s notice sets December 4 [2].

The ratepayer case was made before the filing existed. In January, six senators, among them Peter Welch, Jeanne Shaheen and Edward Markey, wrote that it is “necessary to require tech companies, not American families, to foot the bill for their load” [4]. Chief executive Vamsi Chadalavada replied that data centers had not been a driver of wholesale costs in New England, and that the ISO’s forecast showed annual electricity use rising more than 11% from 2025 to 2034, mainly from heating and transportation [4].

No data center developer had filed in the docket by the close of November 13; the Massachusetts Attorney General had moved to intervene [5].

What I’m watching

  • December 4 or 7, 2026: the comment deadline, and the first developer filings on whether $250/MWh and a seven-year interim service are workable terms [1,2].
  • 2027: the ISO’s detailed bring-your-own-capacity rules, which will say what “new” means [1].

Will FERC accept a cost agreement that binds the retail customer directly? The owners have asked FERC to tell them how to make one work if not [1].

Owen Hollis

Key dates

  • Comment date on ER27-484 under FERC's notice (December 7 requested)
  • Proposed start of large-load applications and studies
  • Proposed start of the new large-load transmission services

What counts as a large load under ISO New England's proposed rules?

A commercial or industrial customer at one site with a gross peak demand of 50 MW or more, connected above 60 kV [1]. Storage, hospitals, water treatment, railroads and airports are excluded, as are campuses without 50 MW of dedicated computing or process load, such as a university without a major data center [1].

When could a data center in New England get the new large-load transmission service?

Applications and studies would start June 1, 2027, and service would start June 1, 2028, if FERC accepts the filing [1]. ISO New England says the gap is the time it needs to build and test the software [1].

Does a New England data center have to bring its own power plant?

For firm service, yes in concept: the customer must designate enough new capacity resources to cover the firm amount it requests [1]. Until it does, it gets interim non-firm service, and the detailed rules, including what counts as new, are to be filed in 2027 [1].

What happens to a non-firm data center when New England power prices spike?

All or part of its interim or non-firm service is re-dispatched when its locational price exceeds $250/MWh, a level ISO New England says load zone prices reached in about 1% of hours from 2021 through 2025 [1].

When are comments due on ISO New England's large-load filing at FERC?

FERC's notice sets 5 p.m. Eastern on December 4, 2026 [2]. ISO New England asked for December 7, and the Electric Power Supply Association supported that request [1,3].

This column draws on ISO New England's transmittal letter and FERC's notice of the filing; it does not draw on the full tariff sheets, the supporting testimony of Dennis Cakert or the affidavit of Alexander Rost except as the letter summarizes them. The proposed rules are a filing, not an accepted tariff, and FERC may accept, reject, modify or sever parts of them. The comment date is December 4, 2026 under FERC's notice; ISO New England and the Electric Power Supply Association have asked FERC to move it to December 7, and FERC had not ruled on that request in the record this column draws on. The filing gives no count of large-load requests in New England or of the megawatts they represent. The views of the New England senators are from their January 2026 letter, written before this filing. No data center developer, state regulator or consumer advocate had filed comments in the docket as of November 13; the Massachusetts Attorney General had moved to intervene, and its position is not yet on the record.

  1. 1Revisions to ISO New England Inc. Transmission, Markets and Services Tariff Related to the Integration of Large Loads to the Transmission System, Docket No. ER27-484-000 (transmittal letter)ISO New England Inc. · November 13, 2026 · elibrary.ferc.gov
  2. 2Combined Notice of Filings #2 (ER27-484-000)Federal Energy Regulatory Commission · November 13, 2026 · elibrary.ferc.gov
  3. 3Answer of the Electric Power Supply Association in Support of ISO-NE Request for Extended Comment Period, Docket No. ER27-484-000Electric Power Supply Association · November 13, 2026 · elibrary.ferc.gov
  4. 4Correspondence between ISO New England and New England senators on data center demand growth (letters of January 23 and February 6, 2026)ISO New England Inc. · February 6, 2026 · iso-ne.com
  5. 5Docket sheet, ER27-484-000Federal Energy Regulatory Commission · accessed 2026-11-15 · elibrary.ferc.gov

Filed under: ISO New England / NEPOOL / large loads / co-location / capacity markets / cost allocation / data centers