Oregon PUC Adopts Pacific Power's Data Center Settlement: Contracts Instead of a Posted Rate, Tariffs Due Nov. 24

Order No. 26-443 in Docket UE 463 approves the stipulation as filed, turns down the Data Center Coalition's request for a stated cost-of-service rate, and agrees with the coalition on one point: exit fees should track actual stranded costs. Schedule 401 takes effect January 1, 2027.

Owen HollisLoad Factor News

Load Ledger
ItemBodyLoadStageSrc
Schedule 401, Service to New Large Energy Use Facilities (Docket UE 463)Public Utility Commission of Oregonapplies at 20 MW or morestipulation adopted Nov. 13, 2026 (Order No. 26-443)[1]
Community Energy Benefits Charge, 1 cent per kWhPacific Power, Oregon100 MW or more of allocated system capacityapproved[1]
Advice No. 25-015 (original Schedule 401 filing)Public Utility Commission of Oregon—permanently suspended[1]
Tariff for large energy use facilities not on Schedule 401Pacific Power, Oregon—due within 60 days of UE 470 rate effective date[1]

The Public Utility Commission of Oregon adopted the Pacific Power data center settlement as filed on Friday. Order No. 26-443 in Docket UE 463, entered November 13 and signed by Chair Letha Tawney and Commissioners Les Perkins and Karin Power, approves the September 16 stipulation, permanently suspends PacifiCorp’s original October 2025 filing, and orders new tariffs by November 24 to take effect January 1, 2027 [1]. The threshold stays at 20 megawatts [3]. The order, like every filing before it, gives no count of the data centers or megawatts that will come in under it.

As this column noted on November 6, when the record closed in UE 463, the open question was whether the Commission would make Pacific Power post a price. It will not.

What the Commission adopted

Schedule 401 is a framework for contracts. Each new large energy use facility, which the POWER Act defines as a site that uses or can use 20 MW and is primarily in NAICS code 518210 computing and hosting [3], signs a LEUF Agreement that the Commission approves within 90 days for a standard contract or 180 days for a non-conforming one [1]. Terms run 10 to 30 years [1].

The menu of charges the order approves:

  • Network upgrades paid upfront, unless the facility is 230 kV or above, sits on a WECC critical path, and data centers make up less than 80% of its presently known capacity need; then the customer pays a proportional monthly fee [1].
  • Energy at the EDAM day-ahead locational marginal price at a node both sides agree on and the Commission approves, and a Peak Demand Charge built from PacifiCorp’s OATT Schedule 1, Schedule 3 and network transmission rates, applied to the customer’s highest monthly demand [1].
  • Generation and storage paid in full, through a monthly Reservation Charge or, where the customer picks its own resources, direct reimbursement plus risk and firming charges [1].
  • A 1 cent per kWh community energy benefits charge on customers with 100 MW or more of allocated system capacity [1].
  • A $25,000 nonrefundable application fee, with engineering studies billed separately [1].

A site that already had a contract before June 16, 2025, becomes a “New LEUF” if serving it requires $10 million or more of new transmission, distribution or generation investment after that date [1]. The Commission called that figure “neither de minimis nor so high as to render it meaningless” [1].

The coalition’s six requests, and how each came out

The Data Center Coalition filed the only opposition. Its October 1 notice said the stipulation “materially improves” PacifiCorp’s original proposal, then asked the Commission to decline it as filed and make six changes [2]. The order takes them in turn.

A stated rate. Denied. The coalition argued that older statutes, including ORS 757.603’s cost-of-service option, still require one [1,2]. The Commission read the POWER Act’s “or” between class allocation and direct assignment as permission for contracts alone, and found each reviewed agreement to be a regulated, cost-based rate [1,3]. It also said a class-wide rate “inherently involves intra-class subsidization,” and that PacifiCorp’s “rural and widely dispersed” territory suits direct contracting, even though it chose a class rate for Portland General Electric [1].

Transmission double-counting. Denied. Direct-assigned facilities come out of the OATT charge calculation, which the Commission found sufficient, and it saw no problem billing peak demand on the customer’s own monthly high rather than the system peak [1]. It accepted the 80% line while conceding that it treats a 79.9% customer differently from an 80% one [1].

Exit fees and collateral. Partly granted. “We agree with DCC that it is reasonable to limit exit fees to the actual stranded cost exposure,” the order says [1]. The stipulation’s list of exit-fee components is now a menu, not a formula, and the Commission expects each fee to fall as exposure falls [1]. Collateral, though, stays on the stipulation’s two-year reassessment rather than the faster step-downs the coalition wanted [1].

The community charge. Denied. The coalition wanted program budgets set first [2]. The Commission said very large loads raise prices for scarce things, “from electrical equipment like transformers to specialized labor,” that cannot be itemized, and matched the PGE rate to avoid “potential arbitrage between service territories” [1].

HB 2021. Denied. New resources acquired to serve a data center must be non-emitting, and a customer served from existing emitting plants must offset the emissions it adds [1]. The Commission held that compliance stays PacifiCorp’s obligation [1].

Existing contracts. No clarification needed, the Commission said; leftover boundary questions go to a later filing [1].

The coalition’s fallback, a review of Schedule 401 by a date certain, was also declined [1]. The stipulating parties had argued PacifiCorp’s next general rate case will likely come in 2028, too soon to judge the tariff [1].

Who carries the cost if a data center leaves

This is where the order moves money most directly. If a customer defaults on a shared Qualified Network Upgrade, PacifiCorp can seek the unrecovered balance from other Oregon customers in a rate case only after showing that fees and collateral fell short, that keeping the line beats selling or removing it, and that the result is just and reasonable [1]. If another large customer takes the capacity within three years, the departing customer’s exit fee is refunded pro rata [1].

Credit is the other gate. At PacifiCorp’s election, a customer must either show creditworthiness, meaning senior unsecured debt rated A- or better (by at least two agencies if more than one rates it), or post collateral covering its exit fee [1]. An already-energized site cannot draw more than its highest measured peak as of November 13 until its agreement is approved [1].

Where the sides stand

PacifiCorp, Commission staff, the Oregon Citizens’ Utility Board, and Community Energy Project, Climate Solutions, Oregon Environmental Council and Sierra Club signed the stipulation [1]. The coalition said in October that it “does not waive any administrative or judicial challenge” to the parallel conclusions in the PGE case [2].

Amazon Data Services did not oppose but asked the Commission to confirm the upgrade rules do not license overbuilding [1]. The Commission said PacifiCorp must still justify what it builds, while noting lines rarely come sized to one request [1].

NewSun lost both of its points. Its bid for study deadlines, and for treating a stalled study as a waiver of PacifiCorp’s exclusive territory, was rejected in favor of a first-come queue reported confidentially to the Commission each quarter at most [1]. Its objection to barring resources in a PacifiCorp or PGE request for proposals from serving data centers was rejected too [1]. On that point the Commission went further than the parties did. “We continue to have some concerns that this provision is not protective enough,” it wrote, since a developer might skip the RFP in favor of a data center deal; a large price gap between the two “will be a red flag” [1].

What I’m watching

  • November 24, 2026: PacifiCorp’s compliance tariffs, then the first LEUF Agreement filed for approval, which will be the first Schedule 401 price anyone can read [1].
  • March 31, 2027: the first biennial report, which the Commission says should cover both 2025 and 2026, with counts and capacity published in ranges until at least four separately owned facilities take service [1].

Rehearing requests are due 60 days after service [1]. Whether the coalition files one, the order does not say.

Owen Hollis

Key dates

  • PacifiCorp files Schedule 401 tariffs consistent with Order No. 26-443
  • Schedule 401 tariffs take effect
  • First biennial large energy use facility report, covering 2025 and 2026

Did the Oregon PUC approve Pacific Power's data center tariff?

Yes. Order No. 26-443, entered November 13, 2026, adopts the September 16 stipulation in Docket UE 463 and directs PacifiCorp to file tariffs by November 24 to take effect January 1, 2027 [1].

Will Oregon data centers on Pacific Power get a posted rate per kWh?

No. The Commission found that the POWER Act allows costs to be directly assigned to each large energy use facility through a contract it reviews, without a class-wide stated rate [1,3]. It rejected the Data Center Coalition's request for a stated cost-of-service option [1,2].

Which data centers does Schedule 401 cover?

New facilities that use or can use 20 MW or more and are primarily engaged in NAICS 518210 computing and hosting services [3]. A site that already had a contract before June 16, 2025, is treated as new if serving it requires $10 million or more of new transmission, distribution or generation investment after that date [1].

How much is the community energy benefits charge on large Oregon data centers?

1 cent per kWh for Schedule 401 customers with 100 MW or more of allocated system capacity, matching the charge set for Portland General Electric in UM 2377 [1]. The money funds energy efficiency, home repairs and distributed resources for energy-burdened customers [1].

Can the Pacific Power data center order be challenged?

A party may seek rehearing or reconsideration within 60 days of service of the order, or petition the Court of Appeals [1]. The Data Center Coalition said in its October filing that it was not waiving any administrative or judicial challenge to the parallel PGE conclusions [2].

This column draws on the Commission's order and on the Data Center Coalition's October 1 filing; it does not draw on any statement from PacifiCorp, the Data Center Coalition or other parties made after the order issued. Positions of the stipulating parties, NewSun and Amazon Data Services are as the order summarizes them. No document in the docket that this column draws on states how many data centers will take service under Schedule 401 or how many megawatts they represent. The compliance tariff due November 24 has not been filed, and its text could differ in detail from the stipulation. Whether any party seeks rehearing or appeals is not known; the 60-day rehearing window runs from the date of service of the order, which the order does not state.

  1. 1Order No. 26-443, In the Matter of PacifiCorp, dba Pacific Power, Advice No. 25-015, Schedule 401, Service to New Large Energy Use Facilities, Docket UE 463Public Utility Commission of Oregon · November 13, 2026 · apps.puc.state.or.us
  2. 2Data Center Coalition's Notice of Opposition, Docket UE 463Data Center Coalition · October 1, 2026 · edocs.puc.state.or.us
  3. 3House Bill 3546 (2025), Enrolled (POWER Act)Oregon Legislative Assembly · accessed 2026-11-14 · olis.oregonlegislature.gov