Fermi's 600 MW Hyperscaler Letter Is Not Yet the 200 MW Lease Texas Tech Requires by Dec. 31 to Let Project Matador Build

Texas Tech can end the Project Matador ground lease if no notice to proceed issues by year end, and that notice waits on a signed Phase 1 lease of at least 200 MW, Fermi's quarterly report says. The new hyperscaler deal is a non-binding letter, and the TensorWave lease is gone.

Owen HollisLoad Factor News

Load Ledger
ItemBodyLoadStageSrc
Hyperscaler letter of intent, Project Matador (customer unnamed)Carson County, Texas (private grid)approximately 600 MW of powered landnon-binding LOI signed Nov. 10, 2026; $200 million prepayment agreement[1]
Texas Tech ground lease notice to proceedTexas Tech University System (landlord)requires a Phase 1 tenant lease of not less than 200 MWcondition not satisfied; deadline Dec. 31, 2026[1]
TensorWave data center leaseFermi Campus 1 LLC, Project Matador—terminated Nov. 10, 2026[1]
Project Matador Nuclear Units 1-4, four AP1000 reactorsU.S. Nuclear Regulatory Commission—draft EIS out; comments due Nov. 23, 2026[3]
West campus air permits 181009, PSDTX1670, GHGPSDTX254Travis County district court, Cause No. D-1-GN-26-002318—petition for review pending[1]

“Issuance of the notice to proceed is conditioned on, among other things, our execution of a lease with a Phase 1 tenant for not less than 200 MW of capacity, which condition has not been satisfied.” That sentence sits in the risk factors of Fermi Inc.’s quarterly report, filed with the SEC on November 12 [1]. The notice comes from the Texas Tech University System, which owns the land under Project Matador in Carson County, Texas, and the report says the system may end the lease if no notice issues by December 31, 2026 [1]. The same day, Fermi announced a 600 MW agreement with an unnamed investment-grade hyperscaler [2]. It is a letter of intent, not a lease [1].

The landlord is a state university system

Fermi signed a 99-year ground lease with Texas Tech on May 14, 2025, for 5,769 acres; an August 2025 amendment set the site at about 4,523 acres, plus a 713-acre tract to be added once a federal agency transfers it to the university system [1]. The lease on the 4,523 acres began in September 2025 [1]. Base rent starts at $1.2 million a year, and once Fermi subleases powered data center space, it owes variable rent of up to 1.0% of the space’s appraised value plus a share of gross revenues [1].

The lease bars vertical construction of data center buildings until Texas Tech issues the notice to proceed [1]. Fermi says it is “in discussions with TTU regarding an extension of the deadline, but there can be no assurance that TTU will agree” [1]. Separately, a collaboration agreement with the university system requires Fermi to put $9.0 million into escrow by December 31 to cover lease payments; it had not been funded as of September 30 [1].

That makes the next step at Project Matador a landlord’s decision, not a regulator’s. Texas Tech’s chancellor, Brandon Creighton, said this week, in a statement Fermi’s release quotes, that “Texas Tech is proud of our partnership with Fermi and remains firmly committed to the success of Project Matador” [2]. The statement does not mention the deadline.

What the hyperscaler signed, and what it did not

As this column reported on October 14, the NRC’s draft environmental impact statement for four reactors at the site arrived while the campus had one tenant lease, with TensorWave, still waiting to close. That lease is over. Its October 31 closing date “passed without extension,” and on November 10 it was terminated under its terms [1]. The AMD credit support agreement tied to it ended too [2].

Also on November 10, Fermi entered the non-binding letter of intent for “approximately 600 megawatts (‘MW’) of powered land” [1]. Attached to it are two signed agreements: a $200 million prepayment agreement and a $15 million early construction and site development agreement [1,2]. A roughly $90 million sale of structural steel and building materials to the customer is still being negotiated [1]. Fermi’s release says the 600 MW would begin in 2027 [2].

Read against the lease condition, the arithmetic is simple. The letter names three times the 200 MW threshold, and the customer has put up money. The condition, as Fermi words it, asks for a signed lease, and the report lists “We may not enter into a definitive lease with the IG Tenant” as its own risk factor [1].

Where the power and the money would come from

Little of this would run through a utility tariff. Project Matador is designed as a behind-the-meter campus on “a private grid built and operated on site,” which Fermi expects to reach about 17 GW if customers sign [2]. The report sizes the first gigawatt: gas use of about 175,000 MMBtu per day for the initial 1 GW of load, after roughly 200 MW of grid power from Southwestern Public Service Company [1]. Early generation is planned as frame-class turbines run in simple cycle, converted later to combined cycle [1].

A third party may carry part of that. Under an August framework agreement, Hillcore Energy Capital would finance, build, own and operate up to about 2.6 GW at a “Hillcore Power Center” on roughly 400 subleased acres, with an initial block of about 360 MW, and Fermi would buy at least half its tenants’ power needs under take-or-pay contracts whose fixed charges pass through to tenants [1]. On November 6 the deadline for definitive documents moved to December 18 [1].

The nuclear piece moved back. Fermi now plans one AP1000 in each of 2034, 2035, 2036 and 2037, which it calls a delay of about a year for the first unit [1]. The NRC’s comment period on the draft EIS runs through November 23 [3].

Two lender dates sit on top of the landlord’s. If Fermi does not deliver an approved customer agreement under its high-voltage equipment loan by December 31, it must prepay that facility; if it does not close committed first-phase project financing by February 10, 2027, its turbine financing goes into default [1]. In October the turbine lenders dropped a separate trigger tied to signing a lease or offtake arrangement for at least 400 MW by November 10 [1].

Where the sides stand

Fermi’s position is that power on hand wins customers. “Hyperscalers want sites that are ready with permitted power, and Fermi’s Project Matador is one of few that can meet that demand today,” chief executive Lee McIntire said in the release [2].

A local group has contested that permitting. Panhandle Taxpayers for Transparency, an association acting through some of its members, asked a Travis County district court on March 27 to reverse the Texas Commission on Environmental Quality’s February 25 order, which denied the group a contested-case hearing and issued Air Quality Permit Nos. 181009, PSDTX1670 and GHGPSDTX254 for the west campus [1]. According to Fermi’s description, the petition alleges the air dispersion modeling failed to show compliance with national ambient air quality standards; it seeks a remand for a hearing, not money [1]. Fermi intervened, calls the challenge “without merit,” and reports no substantive docket activity since May 14 [1].

Shareholders are split too. At Fermi’s October annual meeting, co-founder Rick Perry fell short of reelection to the board under a bylaw requiring a majority of all shares, and the company blamed former chief executive Toby Neugebauer for voting against him, The Texas Tribune reported [4]. Perry can serve until a successor is elected [4]. The Tribune also noted that the stock had fallen more than 90% from its peak [4].

Fermi’s own risk factors add a political note: “candidates who campaigned on restricting data center development were elected to statewide office in several states, including Texas” in November, which the company says may bring more restrictions [1].

What I’m watching

  • December 31, 2026: whether Texas Tech issues the notice to proceed, extends the deadline, or neither, and whether the hyperscaler letter becomes a signed lease of at least 200 MW before then [1].
  • November 23, 2026: the close of NRC comments on the draft EIS for Project Matador Nuclear Units 1-4, Docket ID NRC-2026-0100 [3].

Is a non-binding letter backed by $200 million enough for a university landlord to grant more time? The filings do not say.

Owen Hollis

Key dates

  • Comments due on the NRC draft EIS for Project Matador Nuclear Units 1-4
  • Deadline for definitive documents under Fermi's Hillcore power plant framework, as extended
  • Texas Tech notice-to-proceed deadline; $9 million lease escrow due
  • Deadline to close first-phase project financing under Fermi's turbine financing

Does Fermi's 600 MW hyperscaler deal satisfy the Texas Tech lease condition for Project Matador?

Not as of Fermi's November 12 quarterly report. The notice to proceed requires a signed lease with a Phase 1 tenant for at least 200 MW, and Fermi says that condition has not been satisfied; the hyperscaler agreement is a non-binding letter of intent with prepayment and site-work agreements attached [1].

What happens if Fermi does not get a notice to proceed from Texas Tech by December 31, 2026?

The Texas Tech University System may terminate the ground lease, under which Fermi holds the Project Matador site [1]. Fermi says it is discussing an extension with Texas Tech, with no assurance one will be granted [1].

Why did the Fermi TensorWave lease end?

The October 31, 2026 closing date passed without an extension, and the lease was terminated under its terms on November 10 [1]. The related AMD credit support agreement was also terminated [2].

When do comments close on the NRC draft EIS for the Project Matador reactors?

November 23, 2026 [3]. The NRC says later comments will be considered if practical, but it can ensure consideration only of comments received by that date [3].

When would Project Matador's nuclear units start up?

Fermi's current plan is one Westinghouse AP1000 unit in each of 2034, 2035, 2036 and 2037, about a year later than before for the first unit, subject to licensing and construction [1].

The terms of the Texas Tech ground lease, the notice-to-proceed condition and the status of extension talks are as Fermi describes them in its quarterly report; the Texas Tech University System's own account of those terms, and any position it has taken on an extension, are not in the record this column draws on. The Texas Tech statement quoted here appears in Fermi's earnings release. The hyperscaler is unnamed in every filing, and its letter of intent is non-binding; the 600 MW figure is Fermi's description of 'powered land' to be delivered, not a signed lease or an interconnection request. The air permit challenge is described as Fermi's filing describes it; this column does not draw on the petition itself or on the TCEQ order. Reactor commissioning years are Fermi's plan, not an NRC schedule.

  1. 1Fermi Inc. Quarterly Report on Form 10-Q for the quarter ended September 30, 2026Fermi Inc. · November 12, 2026 · sec.gov
  2. 2Fermi Announces New Agreements with Investment-Grade Hyperscaler and Third Quarter 2026 Financial Results (Form 8-K, Exhibit 99.1)Fermi Inc. · November 12, 2026 · sec.gov
  3. 3Fermi America LLC (dba Fermi America); Project Matador Advanced Energy and Intelligence Campus AP1000 Units 1-4; Project Matador Nuclear Units 1-4; Draft Environmental Impact Statement (91 FR 64702, FR Doc. 2026-20742)U.S. Nuclear Regulatory Commission · October 9, 2026 · federalregister.gov
  4. 4Rick Perry loses reelection to board of Fermi, the data center company he co-foundedThe Texas Tribune · October 30, 2026 · texastribune.org

Filed under: Texas / Fermi America / Project Matador / Texas Tech University System / TCEQ / behind the meter / data center leases