Load Factor Newsby Hollis

Data centers, power demand and the policy fights over both.

Level of government:Grid

Virginia's Executive Order 22 Draws a 25-Megawatt Line for State Help; Local Approval at 25 MW Waits for the Legislature

Gov. Abigail Spanberger's data center order took effect September 18. It cuts large projects out of state site-readiness and fast-track programs and starts agency studies, while local approval, gas limits and cost allocation wait for the 2027 General Assembly.

HollisLoad Factor News

Load Ledger
ItemBodyLoadStageSrc
Executive Order 22: exclusion from VEDP site-readiness and expedited review programsOffice of the Governor of Virginiaanticipated peak demand of 25 MW or greaterin effect September 18, 2026[1]
Local approval required, by-right approval ended, for data centersProposed for the 2027 General Assemblymore than 25 megawattsproposed; no bill text[2]
Priority grid access for data centers meeting clean energy, backup-emissions and on-site gas termsProposed in the framework—proposed[2]
Emergency curtailment procedures for data centers without new capacity under PJM's IRASChief Energy Officer with the SCC and utilities—directed; contingent on FERC approval of IRAS[1]
Data centers pay for transmission built exclusively for themVirginia State Corporation Commission—ordered, summer 2026[4]

Twenty-five megawatts appears twice in Virginia’s new data center package, and the two appearances carry very different weight. In Executive Order 22, which Gov. Abigail Spanberger signed and put into effect on Friday, September 18, 25 MW of anticipated peak demand is the line above which the Virginia Economic Development Partnership may no longer help a new data center through state site-readiness or fast-track programs [1]. In the accompanying framework, “more than 25 megawatts” is the line above which every data center would need local approval, “regardless of prior project approvals” [2]. The first binds the executive branch as of Friday. The second is a bill nobody has filed.

This is the governor’s office, not a commission or a county board, so the question for every item is simple: does the order do it, or does it ask someone else to?

What the order does on day one

Executive Order 22 makes the Office of the Chief Energy Officer the lead for what the governor calls the Virginia Data Center Accountability Framework, with every executive branch agency told to support it on request [1]. Three provisions take hold immediately [1]:

  • Site-readiness and fast track. The Virginia Economic Development Partnership “shall not provide assistance” through the Virginia Business Ready Sites Program, any expedited permitting program or any similar discretionary program “for a new data center project with an anticipated peak electrical demand of 25 MW or greater.”
  • Nondisclosure agreements. Executive branch agencies may not enter into, enforce or require an agreement that keeps material information about a proposed commercial data center, its public incentives, “anticipated resource demands” or community impacts from the public. Existing commitments are honored; national security is the named exception.
  • Cooling water. The Eastern Virginia Groundwater Management Area is designated a cooling water scarcity area, while the Department of Environmental Quality writes the criteria for designating others.

Everything else in the data center half of the order is a study, a workplan or an instruction to advocate. The governor’s own release describes the package as a mix of the order, “immediate directives to state agencies, and proposed legislation for the 2027 General Assembly session” [3].

The studies, and when they come due

The order sets its clocks in days from September 18 [1]. By this column’s count:

  • January 16, 2027 (120 days): the Chief Energy Officer publishes a Data Center Planning and Community Engagement Toolkit for localities, including guidance for evaluating “anticipated electricity demand,” backup generation and air emissions, plus model community benefit agreements [1].
  • March 17, 2027 (180 days): DEQ delivers findings from a cumulative-impact review of diesel and other backup generation, covering the number, capacity, fuel type, expected operating hours and geographic concentration of generators, and measures to move Tier II units to Tier IV controls, batteries or fuel cells [1]. Workplans for the noise rule and the cooling water rule fall on the same date, as does a methane update from the Chief Energy Officer [1].
  • May 16, 2027 (240 days): Virginia Energy recommends where lower-impact development could go: brownfields, edge facilities and regions with infrastructure capacity [1].

The VA-LEAD designation, a tiered score for data centers modeled on LEED and Energy Star, has the longest fuse. Proposed criteria are due by the end of 2027 [1].

Where the cost and power pieces actually sit

For readers who follow who pays, the order’s affordability section is advocacy, not allocation. The Chief Energy Officer is told to engage utilities, the State Corporation Commission and PJM to push for “assigning costs associated with PJM’s Reliability Backstop Procurement to data center large loads causing those costs,” and for equitable cost allocation under PJM’s Interim Resource Adequacy Service, or IRAS [1]. Neither the SCC nor PJM answers to an executive order.

The curtailment directive is conditional twice over. The Chief Energy Officer is to work with the SCC and utilities on emergency curtailment procedures for data centers “who have not brought their own new capacity” under IRAS, “when such proposal is approved by the Federal Energy Regulatory Commission” [1]. Curtailment means cutting a customer’s service when the grid is short. The order says curtailment should go easier on data centers that bring their own clean energy or shave their peaks [1].

The framework goes further on paper. It proposes priority grid access for data centers that source clean energy five years faster than the Virginia Clean Economy Act requires, cut backup generator emissions by 60%, and keep on-site gas to “at most a de minimis allowance,” with the state’s electricity consumption tax doubled for any operator that takes priority access and then falls short [2]. It also calls for “probability-of-dispatch” cost allocation in future SCC rate cases and stronger upfront financial commitments from developers so that speculative projects do not hold grid capacity [2].

At her press conference, Spanberger said, “We are the first in the nation to limit behind-the-meter gas generation” [5]. Behind-the-meter here means gas units on the data center’s side of the utility meter. The order’s text contains no such limit [1]. The framework lists it as a goal, to “the maximum extent practicable” [2].

This builds on one thing already decided. Over the summer, after a filing by the governor’s administration, the SCC ordered data centers to pay for transmission built exclusively to serve them [4]. That was a commission order. Most of what was announced Friday would need the same kind of follow-through from the SCC, PJM or the legislature.

Where the sides stand

The governor framed it as a bar for newcomers. “If you don’t want to meet these high standards, Virginia may not be the place for you,” she said, according to WTVR [5]. Asked whether the rules reach the hundreds of existing facilities, she said, “We are raising the standards for new folks to the game and ensuring that over time the others join in those highest of standards” [5].

The Data Center Coalition said it shared the goals but warned that “significant and abrupt policy changes without meaningful stakeholder engagement could prove unworkable,” WTVR reported [5].

Criticism also came from the other direction. Sen. Glen Sturtevant (R-Chesterfield), who wants a moratorium, called the plan “a Big Tech-friendly plan for more data center growth in Virginia” and wrote that there is “no cap on new data center electric load” [5]. Sen. L. Louise Lucas (D-Portsmouth) said it “does not end the $2 billion in sales tax exemptions provided to data centers” [5]. House Speaker Don Scott took the opposite reading of the same word: “This is a moratorium on bad actors in this industry” [3]. The Sierra Club’s Virginia chapter called the order “the strongest executive action taken on the environmental impacts of data centers in Virginia that we have ever seen” [3].

On local governments, A Holland & Knight analysis reads the order as imposing no binding obligation on counties, cities or towns, which take their zoning power from the General Assembly under the Dillon Rule [6]. The toolkit and VA-LEAD would push localities indirectly, through state incentives [6]. That matters for the kind of record this column found in Stokes County, North Carolina, on September 16, where a 1,849-acre rezoning carried no megawatt figure. A Virginia county could ask the toolkit’s demand questions in January. Nothing in the order makes it.

What I’m watching

First, the toolkit due January 16 by this column’s count, and whether its electricity demand questions ask for a megawatt figure and a service date [1].

Second, the 2027 bills. The 25 MW local approval rule, the gas limit and the probability-of-dispatch allocation exist so far only in an 11-page framework [2]. The threshold that matters to developers is the one that ends up in statute.

Hollis

Key dates

  • Executive Order 22 signed and effective
  • Community engagement toolkit due (120 days, this column's count)
  • DEQ backup-generator findings and noise and cooling-water workplans due (180 days, this column's count)
  • Virginia Energy siting recommendations due (240 days, this column's count)

Does Virginia now require local approval for data centers over 25 MW?

Not yet. Ending by-right approval and requiring local approval above 25 megawatts is a proposal the governor plans to take to the 2027 General Assembly [2,3]. The 25 MW line in Executive Order 22 itself applies only to state site-readiness and expedited review programs run by the Virginia Economic Development Partnership [1].

Does Executive Order 22 ban nondisclosure agreements for data centers in Virginia counties?

The ban covers executive branch agencies and employees under the governor's supervision, and existing agreements are honored [1]. Holland & Knight reads the order as not binding counties, cities or towns [6].

Does Virginia's executive order limit on-site gas generation at data centers?

The order's text contains no gas generation limit [1]. Limiting on-site and behind-the-meter gas generation 'to the maximum extent practicable' is listed in the framework as a goal for later action [2].

When is Virginia DEQ's data center backup generator review due?

Within 180 days of September 18, 2026, which by this column's count is March 17, 2027 [1]. The review covers the number, capacity, fuel type, operating hours and concentration of backup generators [1].

Does the Spanberger data center plan pause new data centers or end the sales tax exemption?

No. The plan includes neither a moratorium nor repeal of the data center sales tax exemption, which drew criticism from Sen. Glen Sturtevant and Sen. L. Louise Lucas [5].

Executive Order 22 states its deadlines in days from September 18, 2026; the calendar dates given here (January 16, March 17 and May 16, 2027) are this column's count, not dates the governor's office published. The framework's legislative items, including local approval above 25 MW and limits on on-site gas generation, had no bill text as of publication, so thresholds and terms could change. Remarks by Sen. Glen Sturtevant, Sen. L. Louise Lucas and the Data Center Coalition are as reported by WTVR. The reading that the order does not bind localities is Holland & Knight's analysis; the governor's office has not addressed that point in the documents this column draws on. PJM's Interim Resource Adequacy Service is referenced in the order as a proposal still awaiting FERC approval.

  1. 1Executive Order 22 (2026): Establishing New Nation-Leading Standards and Initiatives to Implement the Virginia Data Center Accountability Framework and Responding to Unprecedented Risk From Artificial IntelligenceOffice of the Governor of Virginia · September 18, 2026 · governor.virginia.gov
  2. 2Virginia's Data Center Accountability FrameworkOffice of the Governor of Virginia · September 18, 2026 · governor.virginia.gov
  3. 3Governor Spanberger Unveils Nation's Most Comprehensive & Aggressive Data Center Accountability Standards, Signs Executive Order to Immediately Put Into ActionOffice of the Governor of Virginia · September 18, 2026 · governor.virginia.gov
  4. 4NEW: Following Governor Spanberger's Urging, SCC Requires Data Centers to Pay for New Transmission InfrastructureOffice of the Governor of Virginia · August 5, 2026 · governor.virginia.gov
  5. 5Gov. Spanberger proposes new data center rules for Virginia; reaction is mixedWTVR CBS 6 · September 18, 2026 · wtvr.com
  6. 6Virginia's New Data Center Accountability FrameworkHolland & Knight · September 21, 2026 · hklaw.com

Filed under: Governor / Virginia / executive order / on-site generation / cost allocation