Stokes County Rezones 1,849 Acres Next to Belews Creek for Project Delta, 3-2, With No Megawatt Figure on the Record
North Carolina county commissioners approved a hyperscale data center rezoning a second time. The posted conditions govern where generators sit and what fuel backup units burn, but not how much power the campus will draw or who pays to serve it.
| Item | Body | Stage | Src |
|---|---|---|---|
| Project Delta conditional rezoning, R-A to M-2-CZ (Engineered Land Solutions) | Stokes County Board of Commissioners, N.C. | approved 3-2, September 14, 2026 | [7] |
| Planning Board recommendation on Project Delta | Stokes County Planning Board | denial recommended 5-2 | [2] |
| Water service to Project Delta, about 100,000 gallons per day at full build-out | Stokes County Water and Sewer Authority | will-serve letter; contingent | [4] |
The Stokes County Board of Commissioners in North Carolina voted 3-2 on Monday, September 14, to rezone about 1,800 acres of farmland outside Walnut Cove for Project Delta, a hyperscale data center campus proposed by Engineered Land Solutions [5,7]. The site sits beside Duke Energy’s Belews Creek Steam Station [1]. The board has now approved the project twice by the same margin [7].
What the board approved
The application asks to move four parcels totaling about 1,848.74 acres from Residential-Agricultural zoning to a Heavy Manufacturing Conditional Zoning District, M-2-CZ [1]. The property owners are DFC Stokes, LLC and DFC Stokes 2, LLC; the land runs along U.S. 311, Tuttle Road, Oldtown Road and Coon Joyce Road, between Walnut Cove and the Dan River [1]. Conditional zoning in North Carolina means the conditions the developer consents to in writing become part of the zoning itself and run with the land [2].
This was a second pass. The board approved the rezoning 3-2 in January. Residents and nonprofits sued, and a court adopted a joint consent order that voided that vote and added procedural safeguards, including a September 8 special hearing with three hours set aside for public comment [7]. Engineered Land Solutions filed a new application and held a public information meeting on it on July 8 [1].
On August 13 the Planning Board recommended denial, 5-2, finding the proposal inconsistent with the county’s 2035 Vision Plan [2]. That recommendation is advisory under state law [2]. County planning staff had gone the other way, recommending approval as reasonable and in the public interest, on the condition that approval “should rest on the enforceable conditions proposed by the Applicant” [1].
According to WFDD, Chairman Wayne Barneycastle and Commissioner Brad Chandler voted no [6]. Chandler moved to have Commissioner Keith Wood recuse himself over ties to CMC Rebar, a possible materials supplier; the motion drew only Chandler’s vote, and the county attorney said she saw no conflict on the facts known [6].
What the conditions say about power
Here is the gap. The record has the acreage to two decimal places. It has no megawatt figure.
The conditions dated September 8, the last version the county posted before the vote, run to nine sections [3]. Six of them deal with noise, cooling and water, floodplain, lighting, height and buffers [3]. Power gets one short section and one clause:
- The permitted accessory uses include “power generation; substations; electrical infrastructure; natural gas infrastructure,” along with battery backup and generation equipment [3].
- Power generators may not sit within 300 feet of the exterior property boundary [3].
- “The use of diesel fuel for power generation shall be limited to the operation of emergency backup generators” [3].
Read together, diesel is confined to backup and gas-fired generation is allowed. Nothing in the conditions caps generating capacity, limits how many hours on-site units may run, or sets a date by which the campus must take grid service [3]. The staff report says the application “contemplates the use of temporary ‘bridging’ generation pending permanent connection to the electric grid” [1]. Bridging generation means power plants on the site that carry the load until the utility can serve it.
Staff described the power question as outside the zoning case: “Energy demand and grid capacity are similarly matters that will be addressed through the applicable utility interconnection process independent of the zoning approval, though the zoning conditions establish enforceable limits on temporary on-site generation pending permanent interconnection” [1]. The limits in the posted text are about location and fuel. Duration and size are not in it.
The questions were asked. At the developer’s July 8 public information meeting, attendees raised generator quantity, capacity and fuel types, projected demand relative to available grid capacity, curtailment, the timeline for permanent grid connection, and the effect of data center demand on residential electric rates [1].
What the Planning Board wanted, and what the posted text has
The Planning Board’s denial cited, among other concerns, “uncertainty regarding on-site power generation and duration of bridging generation” [2]. Chair Ronnie Tilley attached conditions for commissioners to consider if they approved anyway. Two were about power [2]:
- On-site generation: the applicant would state “the types of generators, total number and generating capacity, and a best estimate of the bridging duration before public utility service comes online.”
- Electric rates: “a binding agreement with Duke Energy funding additional capacity attributable to the project and restricting residential rate increases to not more than 3% every five years.”
Others called for property-line air monitoring with weekly reports, a decommissioning bond and spill liners sized to on-site fuel capacity [2].
None of these appears in the September 8 conditions [3]. The nearest is condition 9, which requires environmental reports, monitoring results and compliance materials exchanged with the North Carolina Department of Environmental Quality on air or water quality to be “provided or made accessible to the County” [3]. That puts any state air permit for on-site generation in the county’s hands. It does not set a limit.
Water is handled more concretely. The Stokes County Water and Sewer Authority’s will-serve letter puts the campus at an estimated 100,000 gallons per day at full build-out, including fire suppression, contingent on system upgrades and on the developer paying “100% of all cost” of the improvements [4]. The conditions bar open-loop cooling and direct withdrawals from streams, rivers, wells and other private sources [3].
Where the sides stand
The developer says the project changed since January. WFDD reported that Drew Nations, the company’s chief executive, pointed to stricter standards on noise, energy generation and water use, and tied the project to teacher pay and faster emergency response [6]. Commissioner Sonya Cox cited voters’ repeated rejection of tax increases and called the project a turning point for county finances, according to WFDD [6].
The revenue figures are the developer’s own. The staff report describes an Engineered Land Solutions estimate of about $50.7 million a year at full build-out, based on an assumed $7.09 billion in assessed value across about 1,050 developable acres; the company labels it illustrative and not a representation of actual value [1]. The Planning Board brief lists the applicant’s projection as “$40 million-plus” [2]. An analysis by economist Michael Hicks, funded by the Southern Environmental Law Center, found the project would produce a fraction of the promised local tax revenue [6,7]. The developer disputes it, saying it assumes a much smaller build-out [6]. Staff also noted that the 2026-27 state budget ended North Carolina’s sales tax exemption on data center electricity purchases, revenue the state collects and distributes rather than the county [1].
Opponents focused on generation. Walnut Cove resident Tim Mabe cited studies on gas turbine exhaust reaching homes more than two miles away, including the town’s three schools, and Megan Kimball of the Southern Environmental Law Center warned of pollution from generators near homes [7]. Chandler objected to being rushed on late changes of this size [7]. Anne Harvey David of the Southern Coalition for Social Justice, which brought the first lawsuit, would not say whether another is planned [6].
What I’m watching
First, the adopted conditions. The county has not yet posted the version the board approved, or the consistency and reasonableness statements state law requires with any rezoning decision [2]. If any of the Planning Board’s power conditions made it into the final text, that is where they will show up.
Second, the interconnection. The staff report pushes demand and grid capacity to the utility process [1]. Neither Duke Energy nor the developer has put a load figure or a service date in the county record. Until one of them does, how long the gas units run is an open number.
Hollis
Key dates
- Planning Board recommends denial, 5-2
- Commissioners' special legislative hearing; conditions updated
- Commissioners approve rezoning, 3-2
Reader questions
Did Stokes County approve the Project Delta data center?
Yes. The Board of Commissioners voted 3-2 on September 14, 2026, to rezone about 1,800 acres near Walnut Cove for the project [5,7]. It was the board's second 3-2 approval; a court voided the January vote [7].
How much power will Project Delta use?
The county record does not say. The staff report states that energy demand and grid capacity will be handled through the utility interconnection process, separate from the zoning decision [1].
Will Project Delta run on natural gas generators?
The posted conditions list power generation and natural gas infrastructure as permitted accessory uses and limit diesel to emergency backup units [3]. The staff report says the application contemplates temporary bridging generation until a grid connection [1], but no document gives the generators' size or how long they would run.
Where will the data center get its water?
The Stokes County Water and Sewer Authority said it will serve an estimated 100,000 gallons per day at full build-out, contingent on system upgrades paid entirely by the developer [4]. The posted conditions bar open-loop cooling and direct withdrawals from rivers, wells and other water sources [3].
Did the Planning Board support the Stokes County data center?
No. It recommended denial 5-2 on August 13, 2026, and proposed extra conditions if commissioners approved anyway, including a binding agreement with Duke Energy on capacity costs and residential rates [2].
A note on sourcing
The conditions described here are the applicant's version dated September 8, the most recent the county had posted before the September 14 vote. Commissioner Brad Chandler objected at the meeting to late changes, so the conditions as adopted may differ; the county had not posted the adopted conditions or its consistency and reasonableness statements as of publication. No document in the county record gives the campus's electric demand in megawatts, the size or fuel of any on-site generation, or a Duke Energy service agreement. Vote details and remarks at the meeting are as reported by WFDD and by the Southern Environmental Law Center, which represented residents in the earlier lawsuit and opposes the project.
Sources
- 1Staff Report, Conditional Zoning District Application, "Project Delta"Stokes County Planning and Inspections Department · August 4, 2026 · co.stokes.nc.us
- 2Executive Brief to the Board of Commissioners: Planning Board recommendation on the Conditional Rezoning Application, "Project Delta"Stokes County Planning and Inspections Department · August 21, 2026 · co.stokes.nc.us
- 3Proposed Zoning Conditions, updated September 8, 2026 (Project Delta)Stokes County Planning and Inspections Department · September 8, 2026 · co.stokes.nc.us
- 4Re: Water Service to Project Delta (will-serve letter)Stokes County Water and Sewer Authority · December 26, 2025 · co.stokes.nc.us
- 5Stokes County votes clear the way for massive, controversial data center in Walnut CoveWFDD · September 14, 2026 · wfae.org
- 6Inside Stokes County's latest vote on the Project Delta data centerWFDD · September 15, 2026 · wfae.org
- 7Stokes County Commissioners Approve Hyperscale Data Center DevelopmentSouthern Environmental Law Center · September 16, 2026 · selc.org
Filed under: North Carolina / Stokes County / Duke Energy / on-site generation