Palm Beach County Denies Project Tango, 5-1: The 600 MW AI Campus Loses Its Expansion, but the 2016 Data Center Rights Stay
Palm Beach County commissioners on July 15 rejected PBA Holdings' request to add about 1.57 million square feet to the Central Park Commerce Center, against a staff recommendation for approval. The site keeps 2,020,000 square feet of approved industrial rights, and two data center plans remain in administrative review.
| Item | Body | Load | Stage | Src |
|---|---|---|---|---|
| Project Tango, DOA/ZV-2025-01602 (add square footage to Central Park Commerce Center MUPD) | Palm Beach County Board of County Commissioners | 600 MW, as reported | denied 5-1, July 15, 2026, without prejudice | [4] |
| Central Park Commerce Center approved master plan | Palm Beach County (approved 2016; amended Jan. 30, 2025) | — | 2,020,000 sq. ft. of approved uses remain | [1] |
| ABN/DRO-2026-01058, WPB Logistics conversion of 1,200,000 sq. ft. warehouse to data center | Palm Beach County Development Review Officer | — | administrative review | [1] |
| Florida large load customer threshold, s. 366.043, F.S. (CS/CS/SB 484) | Florida Legislature | 50 megawatts or more at a single location | law | [2] |
Six hundred megawatts. That is the size news reports gave Project Tango, the AI data center campus PBA Holdings wanted on 202.67 acres off Southern Boulevard in western Palm Beach County [3,7]. The county’s 48-page staff report for the July 15 hearing does not contain a megawatt figure at all [1]. On Wednesday the Palm Beach County Board of County Commissioners voted 5-1 to deny the request, with Commissioner Maria Marino the only yes vote and Mayor Sara Baxter, whose district includes the site, recused [3,6].
The vote did not end the data center. It ended the expansion.
What the board actually voted on
The application was DOA/ZV-2025-01602, a Development Order Amendment to the master plan of the Central Park Commerce Center, a Multiple Use Planned Development under an Economic Development Center land-use designation, plus a parking variance [1]. As revised on April 27, the plan asked for 2,346,564 square feet of warehouse, 1,032,000 square feet of data center and 216,000 square feet of minor utility use, a total of 3,594,564 square feet [1]. The approved master plan allows 2,020,000 [1].
County staff recommended approval. “Staff recommends approval of the requests subject to the Conditions of Approval as indicated in Exhibit C-1 and C-2,” the report says [1]. Those conditions included an 850-foot setback for data center buildings from the east property line, which with the 900 feet already separating the line from the Arden neighborhood and Saddle View Elementary School would give about 1,750 feet [1]. Backup generators would sit at least 800 feet from that line and be tested only between 9 a.m. and 5 p.m. [1]. Water from the county utility was capped at 100,000 gallons a day, and data center discharge would be hauled off-site rather than sent to the county sewer [1]. Battery storage was limited to lithium iron phosphate containers [1].
The Zoning Commission had recommended approval in December and then, on July 2, recommended denial unanimously [1,3]. The board followed the second recommendation. Vice Mayor Marci Woodward, who ran the meeting, said after hearing the experts: “If anything I’m more convinced now than ever that it’s not,” meaning the same kind of data center the county approved in 2016 [5]. The denial was without prejudice, so the developer can revise and refile [4].
The legal hook was land use. The county’s growth plan allows only uses with light industrial characteristics in an Economic Development Center, and it defines light industrial as development that “typically does not create negative impacts on immediately adjoining uses” [1]. Staff had classified a data center as light industrial, like a warehouse [1]. Opponents, including the Western Palm Beach County Alliance, argued a hyperscale AI campus is a heavy industrial use [4].
Where the power and the square footage go from here
Denial leaves the existing entitlement in place. The staff report put it plainly: “denial of the request to increase square footage would not deny the current approval” [1]. The current site plan shows two 100,000-square-foot data center buildings, a 1,200,000-square-foot warehouse and a 6,000-square-foot office [1]. Project attorney Ernie Cox told WPTV after the vote, “Well, that project goes forward. This vote doesn’t have any effect on that” [4].
The larger question is the administrative track. The staff report lists three applications that the Development Review Officer handles without a public hearing [1]. One, DRO-2025-01675, PBA’s own site plan for the larger campus, was contingent on the board approving the amendment [1]. Another, ABN/DRO-2026-01058, comes from WPB Logistics Owner, which owns about 60 acres of the site; it asks to convert the approved 1,200,000-square-foot warehouse into four data center buildings of 294,250 square feet each, plus a 20,000-square-foot water treatment building and generator yards [1,6]. Staff noted that the uses on an Economic Development Center master plan can be changed administratively within the code [1]. Stet News reported that the two owners could each convert roughly 1 million square feet of existing rights, about 2 million square feet of data centers in all, without a commission vote [6].
That is where Woodward pressed staff after the vote. “To be clear we don’t have say-so but the board has given clear direction at this point about how we feel about this use and its compatibility with our comprehensive plan,” she said, asking whether staff would consider that [6].
The power side sits outside the county record. In its justification statement, quoted in the staff report, the applicant said it holds a binding power service agreement with Florida Power & Light: “This FPL power agreement has strict timelines to develop the required substations and AI use needed to accept the power, and to begin utilizing the power” [1]. Staff called the reasons for the change mostly “changes in market demand, technological capabilities, and the Applicant’s business objectives” rather than changes to the property [1]. The agreement’s size and terms are not in the report.
The state law matters here. Florida’s CS/CS/SB 484, Chapter 2026-65, defines a large load customer as one with an anticipated monthly peak of 50 megawatts or more at one location and requires utility tariffs that “reasonably ensure that each large load customer bears its own full cost of service” [2]. Every public utility, FPL included, must file such a tariff by Oct. 1, 2026 [2]. The same law leaves siting with local governments: “Local governments shall maintain the authority to exercise the powers and responsibilities for comprehensive planning and land development regulation granted by law with respect to large load customers” [2]. Wednesday’s vote used that authority.
Data Center Knowledge reported that Jefferies estimates FPL’s capital plan through 2032 carries roughly 6 GW of prospective data center load, about $12 billion of spending [7]. That is the bank’s estimate, not an FPL filing.
Where the sides stand
The developer. PBA Holdings argued the request mostly reallocated rights the land-use ordinance already allowed and would replace an asphalt plant and a concrete plant still operating on the site [1,6]. Marino agreed: “I will take the slings and arrows. But I think this is something that we do need” [6]. After the vote, Cox said in a statement that the company would be “taking time to evaluate our options moving forward” [5]. Stet News reported that the developers valued the full plan at $34.5 billion [6].
County staff. Zoning Director Wendy Hernández disputed the developer’s framing that only about 280,000 square feet of data center was being added. “They are approved for 2,020,000 square feet of EDC uses. They are asking for another 1.5 million square feet,” she told the board, according to Stet News [6].
Residents and the school district. The Palm Beach County School Board wrote of “the potential long-term consequences of placing a hyperscale artificial intelligence facility in such close proximity to a public school” [1]. Ben Brown, an Arden homeowners’ association officer, told WPTV, “Something that size has no business being next to an elementary school or residential community” [5]. More than 80 people signed up to speak [4].
The land next door. WPB Logistics, the other owner, opposed PBA’s application at the Zoning Commission and asked that it be tabled, while pursuing its own data center conversion [1,6].
What I’m watching
Aug. 27, first reading of the county’s data center rules. WLRN reported that the board voted 7-0 this month to advance a moratorium and new regulations for large data centers, with a first reading on Aug. 27 [3]. Project Tango was filed before the pause and was heard anyway [3]. Whether pending administrative conversions such as ABN/DRO-2026-01058 fall under it is not settled in the record [1,6].
Oct. 1, FPL’s large-load tariff. Whatever is built at Central Park Commerce Center will be served under the tariff FPL must file by then [2]. The power agreement the applicant cites predates it, and how the two fit together is an open question.
Owen Hollis
Key dates
- County commission denies Project Tango expansion, 5-1
- First reading of the county's proposed data center regulations, as WLRN reported
- SB 484 deadline for public utilities to file large-load tariffs
Reader questions
Did Palm Beach County stop the Project Tango data center?
It stopped the expansion, not the site. Commissioners denied the request to add square footage 5-1 on July 15, but the 202.67-acre property keeps its approved 2,020,000 square feet of industrial uses, including data center space [1,5].
Can Project Tango apply again?
Yes. The denial was without prejudice, so PBA Holdings can revise and resubmit, though a new application would face whatever rules come out of the county's data center moratorium [4,5].
How much power would Project Tango use?
News reports put it at 600 MW, a figure attributed to the developer's own filings [3,7]. The county staff report does not state a megawatt figure [1].
Does Florida's SB 484 take zoning decisions away from counties?
No. The law says local governments keep their planning and land development powers over large load customers, defined as 50 MW or more at a single site [2].
When does FPL have to file a large-load tariff under SB 484?
By Oct. 1, 2026, each public utility must file a tariff meant to make large load customers bear their own full cost of service [2].
A note on sourcing
The 600 MW figure comes from news reports of the developer's filings; the county staff report gives no megawatt figure, and the FPL power service agreement the applicant describes has not been made public, so its size, timelines and terms are unconfirmed. The Jefferies estimate of FPL's planned data center load is the bank's, as Data Center Knowledge reported it. The $34.5 billion valuation is the developer's figure as Stet News reported it. The county's written resolution of the denial was not yet published as of this column, and the moratorium's terms are as WLRN, WPTV and Stet News described them before any ordinance text. FPL and NextEra had not responded to Data Center Knowledge as of its report, and neither appears in the record this column draws on.
Sources
- 1Zoning Application Staff Report, Board of County Commissioners, July 15, 2026: Project Tango, DOA/ZV-2025-01602 (Central Park Commerce Center MUPD, Control No. 2015-00085)Palm Beach County Zoning Division · July 8, 2026 · discover.pbcgov.org
- 2CS/CS/SB 484, Data Centers, Enrolled Text (Chapter 2026-65, Laws of Florida)Florida Legislature · May 8, 2026 · flsenate.gov
- 3'Not compatible': Palm Beach County rejects controversial Project Tango AI data centerWLRN · July 16, 2026 · wlrn.org
- 4Palm Beach County commissioners reject Project Tango AI data center after more than 12 hours of debateWPTV · July 15, 2026 · wptv.com
- 5Palm Beach County denies Project Tango expansion, but construction on Loxahatchee site continuesWPTV · July 16, 2026 · wptv.com
- 6County denial could bolster behind-scenes case against AI data centerStet News · July 20, 2026 · stetnews.org
- 7Palm Beach Denial Challenges Wall Street's AI Power BetData Center Knowledge · July 17, 2026 · datacenterknowledge.com
Filed under: Florida / Palm Beach County / Project Tango / data centers / Florida Power & Light / SB 484 / large loads