Texas PUC Approves ERCOT's Ride-Through Rule for Data Centers and Crypto Mines: Stay Online Through a Fault or Face Disconnection

The Public Utility Commission of Texas approved NOGRR282 and NPRR1308 on July 9, setting frequency and voltage ride-through standards for computational loads of 75 MW or more from Aug. 1. Data center and industrial groups argued ERCOT has no authority over retail customers; staff said delegated authority is enough.

Owen HollisLoad Factor News

Load Ledger
ItemBodyLoadStageSrc
NOGRR282, Large Computational Load ride-through requirementsPublic Utility Commission of Texas, Project No. 54445—approved July 9, 2026; effective Aug. 1[1]
NPRR1308, Large Computational Load definitionERCOT Nodal Protocols75 MW or greater site peak demand, 50% or more computationalapproved July 9, 2026; effective Aug. 1[4]
Large Load study requests in the ERCOT regionERCOTmore than 438 GWrequested studies, not projects[5]
ERCOT's area threshold for cascading-outage risk from trip-prone computational loadERCOT studies3,200 MWERCOT study finding[5]

“By analogy, whenever an illegally parked car gets towed, there is usually a person negatively impacted.” That sentence, from a Public Utility Commission of Texas staff memo dated July 2, was the answer to the argument that ERCOT cannot regulate a data center [2]. On July 9 the five commissioners signed an order approving ERCOT’s Nodal Operating Guide Revision Request 282 and its companion, NPRR1308 [1]. Starting Aug. 1, data centers and crypto mines of 75 MW or more on the ERCOT grid must ride through frequency and voltage disturbances, and ERCOT can order one off the system if a failure poses an imminent risk [3,4].

What the commission approved

Both revision requests sat in a batch of 21 in Project No. 54445, the docket where the Commission reviews ERCOT rule changes [1]. The order approves each with its market impact statement and adds no conditions [1]. E&E News and Utility Dive both reported the vote as unanimous [9,10].

NPRR1308 creates the class. A Large Computational Load is “A Large Load in which 50% or greater of the Demand at the site consists of power electronic based load, specifically computational load, such as data centers and cryptocurrency mining facilities” [4]. A Large Load is a site with an aggregate peak demand of 75 MW or more behind common points of interconnection [4]. The term began as “Large Electronic Load” and was renamed in April to avoid a clash with an existing acronym [3,4].

NOGRR282 adds two sections to the Nodal Operating Guide [3]:

  • Frequency (Section 2.6.4). Ride through 58.8 to 61.2 Hz continuously, and for 299 seconds in the bands from 57.5 to 58.8 Hz and from 61.2 to 63.0 Hz [3]. A load may use an internal transfer scheme but must be back to 90% of its prior draw within two seconds [3].
  • Voltage (Section 2.15). Ride through 0.90 to 1.10 per unit continuously; 2.0 seconds from 0.80 to 0.90; 0.5 seconds from 0.50 to 0.80; 0.25 seconds from 0.35 to 0.50; and 0.15 seconds below 0.35 [3]. Cooling and mechanical load may trip below 0.35 per unit [3].

The deep-sag rule has two tiers. Loads that complete their interconnection agreements after Nov. 14, 2025, and on or before Jan. 1, 2028, may cut consumption in proportion to the voltage drop “if capable,” or as much as needed to stay connected [3]. After Jan. 1, 2028, a new load must keep drawing power between 0.8 and 0.5 per unit [3].

Who is covered, and what a failure costs

The line is drawn at Nov. 14, 2025, the day ERCOT posted the request [3,6]. A load that was running, or had ERCOT’s written approval to energize, by then is exempt [3]. So is one whose interconnection agreements were signed, construction notice given, funding posted and study approved by that date [3]. A second route covers loads that never needed the interim study: the transmission utility attests before Dec. 31, 2026, that the load will energize between Nov. 14, 2025, and Dec. 31, 2026, ERCOT approves it, and the load actually energizes by year-end [3]. A modification large enough to trigger a new study ends the exemption [3].

Nothing in the rule is a fine. After a failed ride-through, the customer has 90 days to report a root cause, 90 more to submit a plan and 180 to carry it out, unless ERCOT allows longer [3]. The sharper tool is disconnection: if ERCOT decides that continued operation “poses an imminent risk to local or system reliability,” the load stays off until it satisfies ERCOT that it can comply [3].

The compliance cost falls on the customer. ERCOT’s own impact analysis estimates $600,000 to $750,000 a year in staffing to administer the rule and requires no system project [3]. What a mine or data center spends is not in any approved document. The Texas Blockchain Council puts dedicated battery storage, the most-cited fix, at more than $300,000 per MW and as much as $1.6 million per MW [7]. A member’s bench tests on mining hardware showed about 0.027 seconds of ride-through in the 0.50 to 0.80 band, against the 0.5 seconds required [7].

Why ERCOT says it needs this

ERCOT counts 28 events since the start of 2023 in which computational loads of at least 100 MW tripped during voltage or frequency excursions [5]. Its studies found cascading-outage risk once trip-prone computational load in an area exceeds 3,200 MW [5]. Developers have asked ERCOT to study more than 438 GW of Large Load projects, most of them computational [5]. Those are study requests, not projects.

ERCOT also looked at building its way out. Its studies concluded that “for most events, transmission improvements will not be an effective option” to cut the load-loss risk [5].

Where the sides stand

The Data Center Coalition does not oppose ride-through standards but said ERCOT “has not furnished any evidence that data centers have contributed to loss of load or other reliability events following frequency or voltage disturbances in Texas” [6]. Using a chart ERCOT showed at a NERC conference in February, the coalition pointed out that the listed events involved crypto facilities, oil and gas sites and single industrial loads [6]. It asked the Commission to write the standards through a rulemaking enforced by utility tariffs, and failing that to exempt loads energized before Dec. 31, 2027 [6]. The approved rule keeps the Nov. 14, 2025, line [3]. E&E News reported that the coalition maintained after the vote that the Commission, not ERCOT, should have set the requirements [9].

The Texas Blockchain Council said loads can already meet the frequency rules and the voltage rules above 0.80 per unit, and that the gap is in deep sags [7]. It wanted ERCOT to build system strength first through an ancillary services market for inertia and reactive power. “That is like requiring drivers to survive potholes instead of repairing the road,” it wrote [7].

Texas Industrial Energy Consumers said the rule does not seem aimed at its manufacturing members but called direct ERCOT compliance for retail customers “novel and, frankly, dangerous” [8]. Its legal argument was that PURA § 39.151(j), which lists the entity types bound by ERCOT rules, leaves out retail customers [8]. Two industrial consumers, Air Liquide and CMC Steel, cast the only no votes at ERCOT’s Technical Advisory Committee [3].

Commission staff answered that “delegated authority is sufficient” [2]. It rooted ERCOT’s power in PURA § 39.151(d) and the Commission’s delegation in 16 TAC § 25.361(b), and read § 39.151(j) as a duty on the listed entities rather than a limit on everyone else [2]. “There is no debate that voltage and frequency excursions on the transmission network create reliability concerns,” it wrote [2]. The rule disconnects the load, staff said, not the customer [2].

What I’m watching

Aug. 1 and the Dec. 31 attestation window. The rules take effect in 17 days by this column’s count, and transmission utilities have until year-end to attest for loads that never entered the interim study process [3]. How many sites use that route is not in the record.

A second ride-through rule, and a possible lawsuit. ERCOT says it has found ride-through risks from other Large Loads and intends to file a separate request, with requirements that could differ by technology [3]. Opponents raised the possibility of a court challenge after the vote, E&E News reported [9]. Texas Industrial Energy Consumers filed a motion to intervene in the project before the vote [3].

Owen Hollis

Key dates

  • PUCT approves NOGRR282 and NPRR1308
  • Ride-through requirements take effect
  • Last day for exempted loads under the TDSP attestation route to energize
  • Stricter deep-sag voltage rule applies to loads completing interconnection agreements after this date

When do ERCOT's ride-through requirements for data centers take effect?

August 1, 2026, for both NOGRR282 and the companion definition in NPRR1308 [3,4]. The Commission approved both on July 9 [1].

Which data centers have to meet the ERCOT ride-through rule?

Sites with 75 MW or more of peak demand where at least half the demand is computational load, such as data centers and crypto mines [4]. Loads energized or approved to energize by Nov. 14, 2025, and some with signed agreements, funded facilities and completed studies by then, are exempt unless later modified [3].

What happens if a data center trips offline during a grid disturbance in Texas?

The customer has 90 days from ERCOT's request to report the root cause, 90 more to submit a fix and 180 days to carry it out [3]. If ERCOT finds an imminent reliability risk, it can order the load off the grid until it shows it can comply [3].

Does ERCOT have authority to regulate data centers directly?

That is the disputed point. Commission staff said delegated reliability authority under PURA § 39.151(d) is enough, while the Data Center Coalition and Texas Industrial Energy Consumers said § 39.151(j) leaves retail customers out [2,6,8].

How much does it cost a crypto mine or data center to meet the voltage ride-through rule?

No official figure exists. The Texas Blockchain Council estimates dedicated batteries at more than $300,000 and as much as $1.6 million per MW, its own number [7].

The 28 trip events and the 3,200 MW area threshold are ERCOT's figures from its own studies; the Data Center Coalition's reading that none of the events ERCOT presented to NERC involved data centers rests on ERCOT's February 2026 chart, and the two descriptions have not been reconciled in any Commission finding. The Texas Blockchain Council's hardware test results and battery cost range are its own and have not been tested by ERCOT or the Commission; E&E News reported a different per-megawatt compliance estimate from the council's executive director. No party has filed a court challenge in the record this column draws on; the possibility of one is as E&E News reported it. The 17-day count to the effective date is this column's own arithmetic. The order approves the rule without stating how many existing or queued facilities fall under it, and no document here gives that count.

  1. 1Order Approving ERCOT Revision Requests, Project No. 54445, Review of Protocols Adopted by the Independent Organization (Item 162)Public Utility Commission of Texas · July 9, 2026 · interchange.puc.texas.gov
  2. 2Staff Memos and Proposed Order, July 9, 2026 Open Meeting Item No. 23, Project No. 54445 (Item 160)Public Utility Commission of Texas · July 2, 2026 · interchange.puc.texas.gov
  3. 3NOGRR282 PUCT Report, Board Priority: Large Computational Load Ride-Through RequirementsElectric Reliability Council of Texas · July 11, 2026 · ercot.com
  4. 4NPRR1308 PUCT Report, Board Priority: Related to NOGRR282, Large Computational Load Ride-Through RequirementsElectric Reliability Council of Texas · July 11, 2026 · ercot.com
  5. 5Electric Reliability Council of Texas, Inc.'s Comments Regarding Nodal Operating Guide Revision Request 282, Project No. 54445 (Item 150)Electric Reliability Council of Texas · June 12, 2026 · interchange.puc.texas.gov
  6. 6Data Center Coalition Comments on NOGRR282 Large Computational Load Ride-Through Requirements, Project No. 54445 (Item 148)Data Center Coalition · June 12, 2026 · interchange.puc.texas.gov
  7. 7Texas Blockchain Council Comments to Staff on NOGRR 282 and NPRR 1308, Project No. 54445 (Item 147)Texas Blockchain Council · June 12, 2026 · interchange.puc.texas.gov
  8. 8Texas Industrial Energy Consumers' Comments on NOGRR282 by ERCOT Board of Directors, Project No. 54445 (Item 144)Texas Industrial Energy Consumers · June 12, 2026 · interchange.puc.texas.gov
  9. 9Texas approves grid standards to keep data centers onlineE&E News · July 10, 2026 · eenews.net
  10. 10Texas PUC approves ride-through rules for data centersUtility Dive · July 13, 2026 · utilitydive.com

Filed under: Texas / Public Utility Commission of Texas / ride-through / NOGRR282 / large loads / data centers / cryptocurrency mining