Glendale Annexes Project Eagle/Baccara, 6-1: Three Data Centers, 18 Gas Turbines and an APS Substation Come Into the City

The Glendale City Council voted October 27 to annex and rezone a 160-acre West Valley site for Takanock's data center campus and the self-supply gas plant the Arizona Corporation Commission certificated in February at about 700 MW. The city vote settles land use; the air permit and the substation's terms sit elsewhere.

HollisLoad Factor News

Load Ledger
ItemBodyLoadStageSrc
Project Eagle/Baccara annexation and rezoning, about 160 acresGlendale City Council—approved 6-1, Oct. 27, 2026[1]
Baccara Power, LLC gas generation, Certificate of Environmental Compatibility (L-21369A-25-0222-00253)Arizona Corporation Commissionapproximately 700 MWapproved 5-0, Feb. 4, 2026[4]
Pre-annexation development agreement with Baccara Eagle Land, LLC (Resolution R26-42)Glendale City Council—adopted Apr. 28, 2026[6]
Rezoning recommendation, Project EagleGlendale Planning Commission—recommended 4-2, Sept. 24, 2026[7]
APS substation on about 12 acresProject Eagle/Baccara site—planned; about five years to build out, per the developer[1]

About 700 megawatts of gas generation, certificated by the state in February, now sits inside a city. The Glendale City Council voted 6-1 on Tuesday, October 27, to annex and rezone roughly 160 acres in the West Valley for Project Eagle, three data center buildings, and Project Baccara, the gas plant built to power them [1,4]. The megawatt figure is the Arizona Corporation Commission’s. The city-stage record describes turbines and acres instead.

This is a land-use decision by a city council. The commission settled the power plant’s siting certificate in February, and the air permit belongs to a third agency. What Glendale decided is whose rules the campus is built under.

What the council approved

Mayor Jerry Weiers and council members Lupe Conchas, Dianna Guzman, Ray Malnar, Lauren Tolmachoff and Bart Turner voted for the annexation and an associated zoning change; Council member Leandro Baldenegro voted no, the Mesa Independent reported [1]. Neither Baldenegro nor Weiers explained his vote [1]. The Phoenix Business Journal has described the zoning change as a move from heavy industrial to planned area development, according to Bisnow [7].

The site plan as reported [1]:

  • Project Eagle: three data centers of 330,000 square feet each, on about 108 acres.
  • Project Baccara: a natural gas plant with 18 turbines, on 33 acres.
  • APS substation: about 12 acres, which the developers say will take about five years to build out.

The council got here in steps. On April 28 it adopted Resolution R26-42, directing the city to enter a pre-annexation development agreement with Baccara Eagle Land, LLC “to facilitate the annexation and development of properties within unincorporated Maricopa County and within the City’s municipal planning area” [6]. FOX 10 reported that April vote was unanimous [3]. The Glendale Planning Commission recommended the rezoning 4-2 on September 24 [7]. FOX 10 names the developers as Takanock and Montera Infrastructure [3]; Bisnow describes Takanock as Michigan-based [7].

The ordinance also carries conditions. KJZZ reported that it requires the developer to meet standards sent by Luke Air Force Base, including mitigating emissions from the gas turbines and making sure nothing interferes with pilot visibility [2]. Condition No. 12, which Conchas said helped change his vote, requires the developer to help “increase, fund and streamline a fire station” in western Glendale’s 303 corridor [1].

The power plant already had its state certificate

The generation side of this project went through the Arizona Corporation Commission first. On February 4 the commission voted unanimously to approve a Certificate of Environmental Compatibility for Baccara Power, LLC, in Docket L-21369A-25-0222-00253 [4]. The commission’s summary at the time described two data center buildings and “approximately 700 MW of natural gas generators to supply power both to the data center and in support of the regional power grid,” at the northeast corner of Olive Avenue and the Bullard Avenue alignment [4]. The state’s Power Plant and Line Siting Committee had voted 8-1 to approve the certificate in December 2025 [4]. Vice Chair Rachel Walden’s statement put the plant at 700.2 megawatts, on a county island near Luke [5].

Chair Nick Myers drew the same jurisdictional line this column draws. He told the public the commission’s job “is not to approve or deny the data center,” only to ensure the generation and interconnection meet the statutory requirements for a certificate [4].

Two numbers have moved since then. The February description had two data center buildings; the October reporting has three [1,4,7]. No megawatt figure appears in the city-stage reporting, so whether the plant’s size changed with the building count is not something the public record here answers.

Who pays: the gas, the grid and the substation

For ratepayers, the case for this project rests on self-supply. Walden said she voted yes because “the data center will bring its own power solution so that the ratepayers in Irrigation District #7 and APS territories are not bearing any of the costs to power the facility” [5]. She contrasted it with her lone dissent on Tucson Electric Power’s Project Blue contract, which she said “did not go far enough” in protecting ratepayers [5]. The commission’s February summary was shorter: “All expenses will be paid for by the developer” [4].

Earlier this month the commission restated the policy behind that. In an October 9 statement it said it maintains a “growth pays for growth” principle for new high-load customers, using extra-large-load tariffs, long-term minimum capacity agreements, energy service agreements and upfront capital requirements [8]. The same statement said cost allocation between residential and commercial customers is being examined in APS’s pending rate case [8].

Here is the open piece. The plant is described as serving the regional grid as well as the campus, and the site plan reserves 12 acres for an APS substation [1,4]. None of the documents this column draws on says how the plant ties into APS’s system, who pays for that substation, or under what agreement. Self-supply covers the energy. The wires are a separate question, and APS’s own rate case is where the commission says those allocations get decided [8].

On timing, the substation is the long pole as the developers describe it: about five years to build out [1]. The city vote does not shorten that.

Where the sides stand

The developer’s position is that the vote changed jurisdiction more than outcome. Ed Bull, Takanock’s attorney, told the council, “We have the entitlement. That is a private property right,” and said the project would proceed without annexation under its Maricopa County approvals [1]. On water, Bull said EPCOR, not the city, will serve the site, and that the project would use about 25% of the water the parcel used as farmland, with four new wells, a primary and a backup for each project [1].

Council members who voted yes cited infrastructure and city finances. Tolmachoff said “we need the infrastructure” [2]. Conchas said, “I want to ensure that we don’t have to raise any taxes on our residents” [3]. The city estimates $150 million in revenue over the next decade, KJZZ reported [2]. Guzman said, “There has been a lot of misinformation that has been used to frighten people regarding this project” [1].

Opponents, most of them from neighboring Surprise and Waddell, outnumbered supporters 14 to 4 at the hearing, and nearly 11,000 people signed a petition against the project [1]. Their concerns centered on air and water. Resident David Wirth said, “The West Valley already has a low quality of air, and I have breathing problems myself” [2]. April Butler, who lives and works a mile from the site, said, “They don’t have Glendale residents out here. We had no voice really” [3]. Holly Tolmachoff asked why the project needs four new wells if the farm used more water [1]. Sandy Bahr of the Sierra Club said, “Just because burning gas is not as dirty as burning coal does not make it clean” [1]. One speaker, Tom Bacome of Surprise, backed the data centers and opposed the gas plant [1].

As this column noted with Lordstown’s moratorium fight, local land-use records often say little about power. Glendale’s is a partial exception: the generation is on the site plan, in turbines and acres, even if the megawatts live in a state docket.

What I’m watching

APS rate case, decision expected by year-end. The commission has said cost allocation between customer classes is being decided there, and that APS will file its annual power supply adjustor reset after the case concludes [8]. That docket, not Glendale’s, is where substation and large-load cost questions get answered.

The air permit. Walden listed an Arizona Department of Environmental Quality air permit among the conditions in the certificate [5]. With 18 turbines on the site plan and Luke’s emissions standards written into the city ordinance, that permit is the next public record on how much gas this campus burns [1,2].

Hollis

What did the Glendale City Council approve for Project Eagle/Baccara?

On October 27, 2026 it voted 6-1 to annex about 160 acres near Litchfield Road and Olive Avenue from unincorporated Maricopa County and approve an associated zoning change, according to the Mesa Independent [1]. Council member Leandro Baldenegro cast the lone no vote [1].

How much power will the Project Baccara gas plant produce?

The Arizona Corporation Commission's February 2026 certificate covered approximately 700 MW of natural gas generators to supply the data center and support the regional grid; Vice Chair Walden's statement put it at 700.2 MW [4,5]. Reporting on the city vote describes 18 turbines on about 33 acres and gives no megawatt figure [1,7].

Will APS customers pay for the Glendale data center's power?

The commission said in February that all expenses would be paid by the developer, and Vice Chair Walden said APS and Irrigation District #7 ratepayers would not bear the costs of powering the facility [4,5]. The site plan also includes a 12-acre APS substation, and the documents in this column do not say who pays for it [1].

Where will Project Eagle get its water?

EPCOR, not the City of Glendale, is to provide water, and the developers plan four new wells, according to the Mesa Independent [1]. Takanock told the commission in February it would use chillers rather than evaporative cooling and reuse wastewater from a nearby brewery [4].

What permits does Project Eagle/Baccara still need?

Vice Chair Walden listed an Arizona Department of Environmental Quality air permit, a county construction permit, military compatibility approval, and state historic preservation and Game and Fish sign-offs as conditions in the certificate [5]. Bisnow reported that the project received a Luke Air Force Base compatibility permit earlier in 2026 [7].

The vote tally, the names of council members voting each way, the count of public speakers and the project's acreage split are as reported by the Mesa Independent; this column does not draw on the text of the annexation or rezoning ordinances adopted October 27 or on the council's minutes, which had not been posted as of publication. The rezoning from heavy industrial to planned area development is the Phoenix Business Journal's description as cited by Bisnow. The roughly 700 MW generation figure comes from the Arizona Corporation Commission's February 2026 certificate decision, when the project was described as two data center buildings; the city-stage reporting describes three buildings and 18 turbines and gives no megawatt figure, and this column has not confirmed whether the generation capacity changed. The $150 million revenue figure is the city's estimate as reported by KJZZ. No document this column draws on states who pays for the planned APS substation or under what agreement. Takanock and APS made no statement on the vote in the record this column draws on.

  1. 1Glendale council approves annexation of data centers, gas power plantIndependent Newsmedia (Mesa Independent) · October 27, 2026 · yourvalley.net
  2. 2Glendale approves Project Eagle data center developmentKJZZ · October 28, 2026 · kjzz.org
  3. 3Glendale approves 160-acre data center annexation amid neighbor concernsFOX 10 Phoenix · October 28, 2026 · fox10phoenix.com
  4. 4February 4, 2026 Open Meeting HighlightsArizona Corporation Commission · February 6, 2026 · azcc.gov
  5. 5Vice Chair Walden Releases Statement on Project BaccaraArizona Corporation Commission · February 6, 2026 · azcc.gov
  6. 6Resolution No. R26-42, authorizing a pre-annexation development agreement with Baccara Eagle Land, LLCCity of Glendale, Arizona · April 28, 2026 · public.destinyhosted.com
  7. 7Maricopa County Data Center Project Moves Toward Approval Despite PushbackBisnow · September 28, 2026 · bisnow.com
  8. 8ACC StatementArizona Corporation Commission · October 9, 2026 · azcc.gov

Filed under: Arizona / Glendale / annexation / on-site generation / natural gas / Arizona Corporation Commission / APS