Pennsylvania PUC's Tentative Curtailment Order Defines a Data Center at 25 MW and Takes Most of Them Off the Critical-Load List
The commission voted 4-0 on October 1 to seek comment on rewriting its emergency load control rule: utilities would shed IRAS-eligible computational loads first, and a data center keeps critical-load protection only for the share serving a hospital or similar facility. Payment for curtailment waits for November.
| Item | Body | Load | Stage | Src |
|---|---|---|---|---|
| Tentative order on IRAS, pre-emergency and emergency curtailment (52 Pa. Code §§ 57.51-57.54) | Pennsylvania PUC, Docket M-2026-3064961 | — | out for comment; final order targeted Jan. 28, 2027 | [1] |
| Computational Load Site definition | Pennsylvania PUC, draft Appendix | 25 MW at a single point of interconnection, or 50 MW at multiple points on a single feeder | proposed | [1] |
| Technical conference on large computational load cost allocation | Pennsylvania PUC, Docket M-2026-3065062 | — | set for Nov. 17, 2026 | [2] |
| PJM Interim Resource Adequacy Service (ER26-3515) | FERC | — | filed Aug. 13, 2026; Oct. 12 effective date requested | [1] |
| 2028/2029 Base Residual Auction reliability shortfall | PJM, as cited by the Pennsylvania PUC | 6,831 MW | announced July 14, 2026 | [1] |
The Pennsylvania Public Utility Commission voted 4-0 on Thursday, October 1, to put out for comment a tentative order that rebuilds the state’s emergency load control rule around data centers [1,3]. Under the order, in Docket M-2026-3064961, every electric distribution company would shed large computational customers ahead of everyone else when PJM calls on its Interim Resource Adequacy Service, and no data center would be treated as critical load by default [1]. The load gap behind it is PJM’s: a 6,831 MW reliability shortfall for the 2028/2029 delivery year [1].
When this column covered the September 10 motion that set this up, three things were open: the size threshold, which loads count, and what counts as capacity. The appendix answers the first two. The third, and all of the money, it leaves for later.
What the commission put out for comment
For the utilities, which the order calls EDCs, there are three proposals [1].
- A registry. Each EDC would keep a registry of large loads in its territory, “both existing and new,” give PJM the information it requests, and hand the registry to the commission once a year for its load-forecasting oversight under Act 45 of 2025 [1].
- A first-off procedure. Each EDC would revise its procedures to identify large computational customers and their available megawatts, divide PJM’s IRAS requests among them, notify them, and shed the requested amounts “prior to any other load shed from other customers” [1].
- No automatic critical status. Data centers could not be classified as critical load exempt from curtailment in pre-emergency or emergency events, and the commission asks how that prohibition should be defined [1].
The authority is the same as in September: 52 Pa. Code § 57.52, plus the commission’s powers under the Public Utility Code, including 66 Pa.C.S. § 1505(b) on load management programs [1]. The appendix is more than a tariff instruction. It strikes the old § 57.51, on retiring generating units, replaces it with a page of definitions, and drafts two new sections, §§ 57.53 and 57.54 [1]. “Depending on the development of this docket, a rulemaking may follow,” the order says [1].
Comments are due 30 days after the order appears in the Pennsylvania Bulletin, replies 45 days after [1]. The order gives no Bulletin date. A final order directing utilities to file updated procedures is set for the January 28, 2027 public meeting [1]. ABC27 reported that comments can also go by mail to the commission in Harrisburg [3].
Who counts as a Computational Load Site?
The appendix defines a Computational Load Site as a customer or applicant with “an anticipated maximum peak demand of 25 MW at a single point of interconnection or 50 MW at multiple points of interconnection that are interconnect to a single feeder,” mainly housing IT for software, AI training and deployment, cryptocurrency mining, or “other computational activities at a data center” [1]. Manufacturing, as 61 Pa. Code § 32.1 defined it on September 8, 2026, is excluded [1].
So a 40 MW factory is outside the class, which settles one of September’s questions. The threshold also sits below PJM’s. IRAS reaches end-use load with “a peak load of 50 MW or greater” that comes into service after PJM’s deadlines, as the Data Center Coalition describes the filing [4].
The draft is not uniform about which of those sites get cut first. Pre-emergency curtailment under § 57.53 applies “only to certain Computational Load Entity customers that are subject to the Incremental Resource Adequacy Service established by the regional transmission operator as verified by the EDC” [1]. (“Incremental” is a slip; everywhere else the order says Interim.) On this column’s reading, a 30 MW data center lands in the registry and in the emergency tiers, but in a pre-emergency it is cut only if PJM’s own rules put it under IRAS.
Three alert levels, and where a data center sits in each
The draft keys everything to NERC’s Energy Emergency Alert levels [1].
- Pre-Emergency Load Control Event: declared by PJM around EEA Level 1, before Level 2. Utilities curtail eligible computational customers under IRAS through mandatory interruptible rate schedules [1].
- Emergency Load Control Event: after EEA Level 2, before Level 3. Procedures “shall be applicable to all Computational Load Entity customers,” including when the alert comes with a Department of Energy 202(c) order on backup generation, and customers on interruptible schedules curtail under their schedules’ terms [1]. The text does not say what happens at this stage to a site that brought capacity for its full demand.
- Emergency Forced Outage Event: declared by PJM, such as after EEA Level 3, when utilities must cut firm load. Non-Critical load goes before critical load [1].
Critical load has three levels. Level 1 covers hospitals, emergency responders, and critical utility, energy, military and government infrastructure; Level 3 covers residential customers and commercial or industrial sites whose prolonged outage would risk safety or an environmental release [1]. Both exclude computational load sites by name, with or without an uninterruptible power supply (UPS) [1].
Level 2 is the only way in, and it is narrow. A UPS Computational Load Site is protected only for “the portion of energy demand” needed for real-time service to a Level 1 facility, and only once its UPS or backup supply fails, runs out of fuel, or reaches its Department of Environmental Protection permit limits [1]. To qualify, the site attests to its UPS sizing and NFPA 110 classification, gets an attestation from the Level 1 customer under a commercial agreement, electrically separates the equipment serving that customer, and accepts annual inspection [1]. The split goes in an addendum filed with the commission, and a utility may require the site to pay for metering on the segregated load [1].
What it does to cost, and what it leaves out
IRAS would give Pennsylvania utilities four jobs, by the order’s list: carry out PJM’s directives, keep the registry, coordinate with the commission and customers, and run a compensation program consistent with PJM’s tariff [1]. The order takes up the first three. Compensation goes to “a future proceeding after the technical conference scheduled for November 17, 2026” [1]. That conference, under its own docket, M-2026-3065062, runs 9 a.m. to 4 p.m. in Harrisburg, with panelist applications due October 14, initial comments November 13, and post-conference comments December 18 [2].
The tentative order prices nothing. It is silent on who pays for registry work or interruptible schedules, and on the backstop procurement costs that Governor Josh Shapiro’s executive order asked the commission to keep off traditional retail customers [1]. It was drafted around PJM’s filed dates, a September 30 start for the Reliability Backstop Procurement and October 12 for IRAS [1]. FERC accepted the backstop design on September 29 but suspended it and sent cost allocation to a paper hearing, as this column reported on September 30.
The commission’s case for moving now is a study by its contractor, Synapse Energy Economics: with no further policy action and modest capacity growth, the state and PJM miss the one-loss-of-load-event-in-ten-years standard “in every year through 2030,” and do worse with more data center growth [1].
Where the sides stand
The order tracks the governor’s direction closely. It restates his ask that utilities curtail new computational large loads before any other customer unless the customer “has secured new incremental electric capacity for their entire demand” [1].
The Data Center Coalition has not filed in this docket, but it argued at FERC that the states “must take the lead” on retail curtailment and that PJM “should not seek to displace the role of the states by imposing a uniform retail curtailment policy across the PJM region” [4]. Pennsylvania is doing it the state way, as the coalition asked. The content differs from the coalition’s model, though. With the Virginia State Corporation Commission, the coalition proposed state tariffs that would curtail “designated large commercial and industrial customers,” or require their on-site backup generation, “once PJM has exhausted all other available reliability resources” and before broad manual load shed [4]. Pennsylvania’s draft starts earlier, at the pre-emergency stage, and names data centers and crypto miners rather than large industrial customers generally [1].
The coalition also describes its members as supporting “critical public services, including cloud computing, artificial intelligence, emergency response systems, and public safety operations” [4]. The Level 2 test asks each site to prove that link one Level 1 customer at a time, with a signed attestation [1].
The order was served on the Office of Consumer Advocate, the Office of Small Business Advocate, the commission’s enforcement bureau, the Energy Association of Pennsylvania and every EDC [1]. None had filed comments at publication.
What I’m watching
The Pennsylvania Bulletin date, which starts the 30-day comment clock. And November 17: whether the cost conference takes up payment for curtailed data centers, the one IRAS job this order left out.
Owen Hollis
Key dates
- Panelist applications due for the cost allocation technical conference
- Initial comments due for the technical conference
- PUC technical conference on large computational load cost allocation
- Post-conference comments due
- PUC public meeting targeted for the final curtailment order
Reader questions
Which data centers are covered by Pennsylvania's proposed curtailment rules?
A Computational Load Site under the draft is a customer or applicant with an anticipated peak of 25 MW at one point of interconnection, or 50 MW across several points on a single feeder, mainly housing IT for software, AI, crypto mining or other data center computing [1]. Manufacturing facilities are excluded [1].
Can a Pennsylvania data center be classified as critical load in a grid emergency?
Only narrowly. A site with uninterruptible power supply can get Critical Load Level 2 protection for the portion of its demand that provides real-time service to hospitals, emergency responders or other Level 1 facilities, and only after its backup supply fails, runs out of fuel or hits its permit limits [1].
When are comments due on the PUC's data center curtailment tentative order?
Comments are due 30 days after the order is published in the Pennsylvania Bulletin, and reply comments 45 days after publication [1]. The commission plans a final order at its January 28, 2027 public meeting [1].
Will Pennsylvania data centers be paid when they are curtailed under IRAS?
The tentative order does not say. It leaves a compensation program to a future proceeding after the November 17, 2026 technical conference on large computational load cost allocation [1,2].
How do I apply to speak at the PUC's large computational load cost allocation conference?
Panelist applications are due October 14, 2026, through the commission's website or by email to CLCATechConference@pa.gov; initial comments are due November 13 and post-conference comments December 18 [2].
A note on sourcing
The tentative order is a proposal. It changes no utility tariff or load control plan, and its text may change after comments; a final order is targeted for January 28, 2027. The vote count is as ABC27 reported it; the order lists four commissioners present. The order does not state when it will appear in the Pennsylvania Bulletin, so the comment deadlines have no calendar date yet. The reading that pre-emergency curtailment reaches only sites that PJM's rules make subject to IRAS, while the emergency tier reaches every Computational Load Site, is this column's reading of draft Section 57.53; the emergency-tier text does not say how it treats sites that brought their own capacity. PJM's IRAS proposal was pending at FERC in the record this column draws on, and the order is written around it as filed. The Data Center Coalition's position comes from its FERC protest of IRAS, not from any filing in the Pennsylvania docket. No comments on the order had been filed in the docket at publication, and this column does not draw on positions of Pennsylvania utilities or the Office of Consumer Advocate.
Sources
- 1Tentative Order, Electric Distribution Company Interim Resource Adequacy Service, Pre-Emergency and Emergency Response Provisions, Docket No. M-2026-3064961 (with Appendix)Pennsylvania Public Utility Commission · October 1, 2026 · puc.pa.gov
- 2Secretarial Letter: Technical Conference on Large Computational Load Cost Allocation, Docket No. M-2026-3065062Pennsylvania Public Utility Commission · September 22, 2026 · puc.pa.gov
- 3Pennsylvania utility regulators consider rule to curtail data center power in emergenciesABC27 (WHTM) · October 1, 2026 · abc27.com
- 4Motion to Intervene and Protest of the Data Center Coalition, Docket No. ER26-3515-000Data Center Coalition · September 3, 2026 · elibrary.ferc.gov
Filed under: Pennsylvania / curtailment / critical load / large load / utility commissions