Virginia SCC Orders Dominion to Charge Data Centers Up Front for Their Own Substations, and Leaves the Bigger Lines for Later
The SCC's July 31 Rider T1 order cuts the typical residential increase from $2.90 to $0.94 a month and directs Dominion to write a mandatory contribution in aid of construction for 'direct connect' transmission. Upstream costs, and the co-op boundary, go to a new docket.
| Item | Body | Stage | Src |
|---|---|---|---|
| Dominion Rider T1 (PJM transmission costs), rate year Sept. 2026-Aug. 2027 | Virginia SCC, Case No. PUR-2026-00056 | approved July 31; $1,538,974,037 revenue requirement | [1] |
| Mandatory CIAC for 'direct connect' transmission serving new large loads | Virginia SCC, new docket (number not yet assigned) | Dominion filing due within 90 days | [1] |
| Direct assignment of higher-order transmission costs to GS-5 class | Virginia SCC, new docket | may be considered; not decided | [1] |
| Cost assignment across Dominion Zone co-ops and other EDCs | Mutual Operating Agreements on file at FERC | status update due within 120 days | [1] |
| AEP Ohio data center return to default service | PUCO, Case 26-113-EL-ATA | finding and order Aug. 5 | [5] |
Ninety-four cents. That is what the Virginia State Corporation Commission says a typical Dominion Energy Virginia household using 1,000 kilowatt-hours will see added to its monthly bill from the company’s revised transmission rider, down from the $2.90 Dominion projected when it filed [1]. The bill figure is the smaller part of the July 31 final order in Case No. PUR-2026-00056. The larger part is a directive: Dominion must write a rule that makes new data centers pay up front for the substations and lines built only to connect them [1].
The order has drawn a week of statements since. Gov. Abigail Spanberger’s office claimed credit on Aug. 5 [3], and the Piedmont Environmental Council, which testified in the case, sent supporters a second alert on Aug. 10 [4]. Read against the order, the claims run ahead of what was decided.
What the SCC decided in the Rider T1 case
The case is Dominion’s annual recovery of what it pays PJM Interconnection for transmission service, collected partly in base rates and partly through an adjustable charge called Rider T1 [1]. Dominion filed May 1, 2026, for a rate year running Sept. 1, 2026, through Aug. 31, 2027 [1]. The commission held hearings July 14 through 16 [1].
On the money itself, the SCC had little choice. Under Virginia Code § 56-585.1 A 4, these PJM charges are “deemed reasonable and prudent,” and the order says “the Commission is without discretion to add or subtract from these costs” [1]. It approved a total revenue requirement of $1,538,974,037: $598,621,989 through base rates and $940,352,048 through Rider T1 [1]. Dominion’s application put the total at $206,899,352 above what current rates would produce [1]. The rider takes effect for service on and after Sept. 1 [1].
Where the commission did have discretion was in who pays. It approved an amended 12 coincident peak method, which spreads costs by each class’s share of the system’s 12 monthly peaks, with two changes [1]. One adjusts class allocations to forecast billing units for the rate year; as Dominion explained it, rapid large-load growth means the adjustment produces lower rates for the other classes [1]. The other applies the 85% minimum transmission demand charge for large-load customers that begins Jan. 1, 2027, treating those customers as if they draw at least 85% of contract demand [1]. “At the extremes,” the order says, that cuts the residential class’s allocation factor by 2.84% and raises the GS-4 class’s by 4.33% [1]. Staff, Dominion, the Virginia Committee for Fair Utility Rates and the Attorney General’s Division of Consumer Counsel supported the method [1].
The contribution in aid of construction: what it covers
The order sorted the parties’ direct-assignment proposals into three tiers: “direct connect” facilities such as transmission substations; supplemental projects caused by large-load interconnections; and backbone upgrades, including Regional Transmission Expansion Plan projects, that large loads benefit from along with others [1].
It acted on the first tier only. Dominion must file, after coordinating with staff, amendments to its line extension policy “that would require a mandatory CIAC for defined types of transmission facilities,” within 90 days [1]. A CIAC, or contribution in aid of construction, is a payment the customer makes toward the capital cost up front. The order defines the reach narrowly: the policy applies prospectively and covers “direct connect” facilities, “generally meaning substations and the lines connecting the customer to the bulk transmission system,” where a new or expanding large-load customer is the but-for cause [1]. Dominion is to propose an explicit definition when it files [1].
The charge is net of revenue, as Dominion’s distribution line extensions already are: projected revenue from the customer is credited against the capital cost, and the customer pays the rest [1]. The order limits that credit to revenue from the customer’s transmission charges [1]. It also tells Dominion and staff to consider how the CIAC “can be used to offset or reduce collateral requirements in an equitable manner” [1]. That last point matters for developers. A PEC witness testified that a CIAC “would completely eliminate all risk [of stranded costs] going forward” [1]. The commission did not say whether a data center that pays up front should post less security; it asked Dominion to propose an answer.
Neither the order nor the parties’ statements in the record this column draws on estimate what the contribution will total, or name a project it would apply to. As this column noted on Aug. 6, the cost of serving a large load depends on terms set outside the headline; here the terms are not yet written.
What it leaves for the next docket
The upstream tiers stay open. The order says a direct-connect policy “may not address all instances” of reliability costs that appear to be caused by large loads, and that the record “supports a more deliberate approach to the question of direct assignment of higher-order transmission costs” [1]. In the new docket the commission may consider extending the CIAC to those costs, “a blended approach” that sends higher-order supplemental costs to the GS-5 large-load class, or keeping to direct connect alone [1]. A footnote adds a planning angle: if Dominion has a financial reason to avoid triggering a CIAC, extending the policy to supplemental projects “could drive more regional planning” [1]. The commission also noted that FERC is considering reforms that may overlap with state efforts [1].
The second open question is the territory boundary. Old Dominion Electric Cooperative asked that large-load transmission costs in the Dominion zone be assigned to large-load customers regardless of which utility serves them [1]. The SCC said its jurisdiction covers Dominion’s own retail customers and sent the cross-utility question to the Mutual Operating Agreements on file at FERC, calling it “an equity issue that can go in both directions” [1]. Dominion must work with ODEC and other distribution utilities toward “an acceptable and symmetrical approach” and file a status update within 120 days [1].
Where the sides stand
Dominion opposed direct assignment in the case, arguing the new minimum demand charges should be allowed to mature first; its preferred fallback was assigning costs to the GS-5 class where a transmission certificate case finds GS-5 load driving need [1]. After the order, spokesman Jeremy Slayton said: “When we file our amended line extension policy, we will be adding even more protections for our residential customers to ensure our more energy intensive customers continue to pay their fair share” [3].
Data center companies wanted contributions to be optional. Amazon proposed a voluntary CIAC “as a way to reduce ratepayer burden,” asked that customers electing it “receive top priority in Dominion’s interconnection queue,” and opposed mandatory direct allocation [1]. Google supported a voluntary CIAC for substations, with ongoing maintenance shared by the system [1]. The commission made it mandatory.
Ratepayer and environmental groups asked for more. Appalachian Voices argued for assigning supplemental project costs to the customers driving them; Sierra Club and NRDC sought a CIAC with refunds for everything from the meter to the backbone [1]. PEC president Chris Miller called the order a precedent but said it “does not resolve who should pay for the billions of dollars in other supplemental and regional transmission projects driven by unprecedented data center growth in Virginia” [2]. PEC’s Aug. 10 alert adds that the change is “not retroactive,” so already-approved lines such as Germanna in Culpeper and Daves Store in Prince William County stay spread across all customers [4].
The governor said the order “makes sure that data centers are paying the full cost of the transmission infrastructure their developments require” [3]. That holds for direct connect facilities once a policy is approved. It does not yet hold for supplemental or regional lines [1].
Ohio moved on a different cost the same week. On Aug. 5 the Public Utilities Commission of Ohio ordered AEP Ohio, in Case 26-113-EL-ATA, to require 180 days’ notice before a data center returns to default service, then buy its energy through separate auctions or spot purchases with “the entirety of the cost assigned to the data center customer” [5]. Virginia’s order is about wires; Ohio’s is about energy supply.
What I’m watching
About Oct. 29. Dominion’s amended line extension policy, due 90 days from the order by this column’s count [1]. The first things to read: its definition of “direct connect,” and whether a CIAC lowers collateral.
About Nov. 28. The Dominion-ODEC status update on cross-territory costs, due in 120 days by this column’s count [1].
Owen Hollis
Key dates
- SCC final order in PUR-2026-00056
- Revised Rider T1 takes effect
- Dominion's amended line extension policy due (90 days; this column's count)
- Dominion-ODEC cost assignment status update due (120 days; this column's count)
- 85% minimum transmission demand charge for large loads begins
Reader questions
Do Virginia data centers now have to pay for their own transmission lines?
For one category, going forward. The SCC directed Dominion to propose a mandatory contribution in aid of construction for 'direct connect' facilities, generally substations and the lines tying a new or expanding large-load customer to the bulk system [1]. Larger upstream projects are not covered yet [1,2].
How much will Dominion's Rider T1 change raise residential bills?
The SCC's approved method cuts the projected monthly increase for a typical residential customer using 1,000 kWh from $2.90 to $0.94, starting with service on Sept. 1, 2026 [1].
When does Dominion have to file its amended line extension policy?
Within 90 days of the July 31, 2026 final order, in a separate docket the SCC said it would establish [1]. By this column's count that is Oct. 29 [1].
Does the SCC order apply to transmission lines already approved for data centers?
No. The line extension change applies prospectively [1], and the Piedmont Environmental Council notes that approved projects such as the Germanna and Daves Store lines will still be spread across all ratepayers [4].
Did Amazon and Google support paying for transmission up front?
Only on a voluntary basis. Amazon proposed a voluntary contribution in exchange for top queue priority and opposed mandatory direct assignment; Google supported a voluntary contribution for substations [1]. The SCC made it mandatory for direct connect facilities [1].
A note on sourcing
The new docket the SCC said it would open for Dominion's amended line extension policy had no case number in the record this column draws on. The Oct. 29 and Nov. 28 filing dates are this column's count of 90 and 120 days from the July 31 order; the order itself states only the day counts. The governor's office's estimate that the order will save Virginians 'hundreds of millions of dollars' is its own, as reported by WDBJ; the order does not put a dollar figure on the savings from the contribution requirement, and no transmission project or megawatt figure is named in it. Positions of Amazon, Google, ODEC, Appalachian Voices and others are described as the order summarizes their testimony. The Ohio order is described from the PUCO's release; this column does not draw on the order text in Case 26-113-EL-ATA.
Sources
- 1Final Order, Application of Virginia Electric and Power Company for approval of a rate adjustment clause pursuant to § 56-585.1 A 4 of the Code of Virginia, Case No. PUR-2026-00056Virginia State Corporation Commission · July 31, 2026 · scc.virginia.gov
- 2Press Release: The Virginia State Corporation Commission takes important first step of requiring large-load data centers to pay for transmission facilities constructed solely to serve themPiedmont Environmental Council · August 3, 2026 · pecva.org
- 3Virginia to require data centers to pay for new transmission infrastructureWDBJ7 · August 5, 2026 · wdbj7.com
- 4State Corporation Commission Says Virginians Should Not Pay for Data Center Transmission InfrastructurePiedmont Environmental Council · August 10, 2026 · pecva.org
- 5PUCO sets process to protect AEP Ohio customers from potential data center energy costsPublic Utilities Commission of Ohio · August 5, 2026 · content.govdelivery.com
Filed under: Virginia / Virginia SCC / Dominion Energy / transmission cost allocation / Rider T1 / contribution in aid of construction / GS-5